| Project | AMRUT-Integrated Calicut Water Supply Project Phase-2,Laying Diistribution Lines in Pottamel Zone |
|---|---|
| Project Code | CLTGOI0118511P4 |
| Type | Package |
| Main Project | AMRUT-Integrated Calicut Water Supply Project Phase-2,Laying Distribution Lines in 10 Zone in Kozhikode corporation |
| Funding Agency | AMRUT |
| Category | AMRUT |
| Type of scheme | Water Supply |
| Scheme | AMRUT |
| Description | AMRUT-Integrated Calicut Water Supply Project Phase-2,Laying Diistribution Lines in Pottamel Zone |
| Status | Completed |
| District | Kozhikkode |
| Executing Office | Kozhikode Project Dn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 67000000 |
| TS Number | TS/1900/2018-2019 |
| Technical specification | Scope of Work- Supplying and Laying-110mm PVC pipe-38370m 100mm GI Pipe-500m |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 28/11/2018 |
|---|---|
| Scheduled date of Completion as per agreement | 13 Nov 2019 |
| Expected date of Completion | 31/12/2020 |
| AS Date | 01 Jan 2018 |
|---|---|
| TS Date | 19 Sep 2018 |
| Estimate Approval | 19 Sep 2018 |
| NIT Approval | 25 Sep 2018 |
| Tender Closing | 20 Oct 2018 |
| Price bid opening | 23 Oct 2018 |
| CE Approval | 13 Nov 2018 |
|---|---|
| Final Approval | 13 Nov 2018 |
| Workorder Date | 14 Nov 2018 |
| NA | 28 Nov 2018 |
| Kozhikode Project Dn AE5 |
| Date: 22/09/2021 |
Work has been completed | 100% Completed
Work completed, Total expenditure Rs.40652452/- final Bill paid to contractor on 26.02.2021 including Road restoration charges ..
| Kozhikode Project Dn AE2 |
| Date: 21/04/2021 |
Work has been completed | 100% Completed
work completed.