WSS to Konni-Aruvappualm & Kalanjoor(part) pts: Providing 8700FHTCs & distribution lines in Kalanjoor Panchayath.

Project WSS to Konni-Aruvappualm & Kalanjoor(part) pts: Providing 8700FHTCs & distribution lines in Kalanjoor Panchayath.
Project Code PTAJJM052214979
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description WSS to Konni-Aruvappualm & Kalanjoor(part) pts: Providing 8700FHTCs & distribution lines in Kalanjoor Panchayath.
Status On-going
District Pathanamthitta
Executing Office Konni Sn
AS Amount (Rs) 770000000
AS Number G.O.(Rt)No.401/2022/WRD
TS Amount (Rs) 381000000
TS Number TS/9495/2022_26_1_1
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date Date is not specified
Coverage Providing 8700FHTCs & distribution lines in Kalanjoor Panchayath

Packages

No. Project Name Location View
1 WSS to Konni-Aruvappualm & Kalanjoor(part) pts: Providing 8700FHTCs & distribution lines in Kalanjoor Panchayath. Konni Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
26 Jun 2024 Total tagged -218 nos Pipe laid - 90 to 160 mm PVC - 49.25 km Konni PH Sn - AE
24 Jun 2024 Total tagged -218 nos Pipe laid - 90 to 160 mm PVC - 49.25 km Konni PH Sn - AE
16 May 2024 Total tagged -208 nos Pipe laid - 90 to 160 mm PVC - 48.141 km Konni PH Sn - AE
23 Apr 2024 Total tagged -208 nos Pipe laid - 90 to 160 mm PVC - 47.642 km Konni PH Sn - AE
08 Apr 2024 Total tagged -110 nos Pipe laid - 90 to 160 mm PVC - 47.6 km Konni PH Sn - AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 12/05/2023
Scheduled date of Completion of the Project 13 Aug 2024
Expected date of Completion 13/08/2024

Processing Dates

AS Date 13 May 2022
TS Date 22 Dec 2022

Other details

Project Officers View