Jal Jeevan Mission (JJM) - 2022-23 - CWSS to 13 Panchayath based on Malankara Resorvoir (Package -2)

Project Jal Jeevan Mission (JJM) - 2022-23 - CWSS to 13 Panchayath based on Malankara Resorvoir (Package -2)
Project Code KTMJJM102214715P2
Type Package
Main Project Jal Jeevan Mission (JJM) - 2022-23 - CWSS to 13 Panchayath based on Malankara Resorvoir
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description Jal Jeevan Mission (JJM) - 2022-23 - CWSS to 13 Panchayath based on Malankara Resorvoir (Package -2) -(1) Design, and construction of 45 MLD Water Treatment Plant (Lamella type), (2) Clear watersump etc at Neeloor, (3) Supplying &Laying part of RWPM from Pothichottupara to WTP at Neeloor, (4) Supplying and Laying 150mm DI K9 pumping/conveyance main(s) from WTP at Neeloor to GLSR at Njallikunnu, (5) Supplying and Laying 450 mm/200mm DI K9 conveyance lines from WTP, (6) Supplying and Laying 700mm DI K9 Gravity main from WTP to Sump cum pump house at Vettiparambu etc.
Status On-going
District Kottayam
Executing Office Kottayam Project Dn
Agreement Number
Agreement Date
TS Amount (Rs)
TS Number WRD/KWA-CE(SR)/EST_TS/7902/2022_5_2_1
Technical specification

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 08/06/2023
Scheduled date of Completion as per agreement 31 Aug 2024
Expected date of Completion 31/10/2023

Processing Dates

TS Date 17 Feb 2023
Technichal Pre-Qualification 16 Mar 2023

Approval Dates

Workorder Date 31 May 2023
NA 07 Jun 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Meenachal-Malankara Project Dn AE
Date: 06/11/2023

Work in progress | 3% Completed

Supplied 0.198/1.25 km of 1000mm DI pipe and 1.056/18.8 km of 700 mm DI pipe. Laid 0.088 km of 700 mm DI pipe on Aniyalappu -Vettiparambu road..

Attached images

img

Meenachal-Malankara Project Dn AE
Date: 03/11/2023

Work in progress | 2% Completed

Supplied 0.198/1.25 km of 1000mm DI pipe and 1.056/18.8 km of 700 mm DI pipe. Laid 0.077 km of 700 mm DI pipe on Aniyalappu -Vettiparambu road..

Attached images