| Project | Deposit work of Kundara Panchayath- BAWSS Kundara and adjoining pts. - Pipe line extension in various wards of Kundara Panchayath |
|---|---|
| Project Code | KLMDEPO042211060P1 |
| Type | Package |
| Main Project | Deposit work of Kundara Panchayath- BAWSS Kundara and adjoining pts. - Pipe line extension in various wards of Kundara Panchayath |
| Funding Agency | DEPO |
| Category | Deposit Work |
| Type of scheme | Water Supply |
| Scheme | DEPO |
| Description | Deposit work of Kundara Panchayath- BAWSS Kundara and adjoining pts. - Pipe line extension in various wards of Kundara Panchayath |
| Status | Completed |
| District | Kollam |
| Executing Office | Kundara PH Sn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 702800 |
| TS Number | TS/2022-2023/2022/11982 |
| Technical specification | Deposit work of Kundara Panchayath- BAWSS Kundara and adjoining pts. - Pipe line extension in various wards of Kundara Panchayath |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 30/04/2022 |
|---|---|
| Scheduled date of Completion as per agreement | 16 Jun 2022 |
| Expected date of Completion | 16/06/2022 |
| TS Date | 08 Apr 2022 |
|---|---|
| Estimate Approval | 08 Apr 2022 |
| NIT Approval | 08 Apr 2022 |
| Tender Closing | 15 Apr 2022 |
| Technichal Pre-Qualification | 08 Apr 2022 |
| Price bid opening | 27 Apr 2022 |
| Workorder Date | 30 Apr 2022 |
|---|---|
| NA | 17 May 2022 |
| Kottarakkara PH Dn EE |
| Date: 04/07/2022 |
Work has been completed | 100% Completed
Work Completed.
| Kottarakkara PH Dn EE |
| Date: 25/06/2022 |
Work in progress | 50% Completed
pipe laying work in progress.