JJM-2020-21 Providing FHTC in Cheekode Grama panchayth in Malappuram District
Project |
JJM-2020-21 Providing FHTC in Cheekode Grama panchayth in Malappuram District |
Project Code |
MLPJJM08203220 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
JJM-2020-21 Providing FHTC in Cheekode Grama panchayth in Malappuram District |
Status |
On-going |
District |
Malappuram |
Executing Office |
Malappuram Project Dn |
AS Amount (Rs) |
383900000
|
AS Number |
GO (Rt) no 541/2020/WRD |
TS Amount (Rs) |
334200000 |
TS Number |
15227/2021-22 |
Total Bill Submitted (Rs) |
144858437 |
Total Bill Paid (Rs) |
144858437 |
Population Benefitted |
46252 |
Capacity in MLD |
41.00 |
Actual Project Completion Date |
31 Oct 2022 |
Coverage |
full coverage |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
FHTC in Cheekode GP |
Project Division Malappuram |
|
2 |
Providing balance Distribution with FHTC including PWD/LSGD Road restoration in Cheekode Grama Panchayath-Pipeline Work |
Project Division Malappuram |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
20 May 2024 |
Providing balance Distribution with FHTC including PWD/LSGD Road restoration in Cheekode Grama Panchayath-Pipeline Work-GSB work, leak rectification, consumer work. |
Malapuram Proj Dn AE 4 |
|
14 Feb 2024 |
GI work & house connection work
|
Malapuram Proj Dn AE 4 |
|
10 Jul 2023 |
The work short closed as the lack of road cutting permission from PWD and shortage of GI pipe in rural concrete roads also the contractor not willing to execute the work in time extension. Estimate for the Balance works and FHTCs prepared and submitted. |
Malapuram Proj Dn AE 4 |
|
24 Jun 2023 |
Consumer work and house connection works are on going
|
Malapuram Proj Dn AE 4 |
|
15 Jun 2023 |
Omanoor high school road houseconnection work |
Malapuram Proj Dn AE 4 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
31/07/2021 |
Scheduled date of Completion of the Project |
22 Jun 2024 |
Expected date of Completion |
22/06/2024 |
Processing Dates
AS Date |
23 Feb 2022 |
TS Date |
11 Apr 2023 |