Project | JJM-WSS to Koratty and Kadukutty Panchayath in Thrissur district providing 900 FHTC's and streetmain extension at Koratty Panchayath ongoing (MVS), Part 1 |
---|---|
Project Code | TCRJJM08207125P8 |
Type | Package |
Main Project | JJM-WSS to Koratty and Kadukutty Panchayath in Thrissur district providing FHTC and streetmain extension at Koratty Panchayath ongoing (MVS) |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | JJM-WSS to Koratty and Kadukutty Panchayath in Thrissur district providing 900 FHTC's and streetmain extension at Koratty Panchayath ongoing (MVS), Part 1 |
Status | On-going |
District | Thrissur |
Executing Office | Nattika Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 40910000 |
TS Number | TS/2020-21/2020/22628 |
Technical specification | |
Contractor | BENNY E V (Mob: 9544124440) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 29/04/2021 |
---|---|
Scheduled date of Completion as per agreement | 28 Oct 2021 |
Expected date of Completion | 28/10/2021 |
TS Date | 24 Oct 2020 |
---|---|
Estimate Approval | 24 Oct 2020 |
Tender Closing | 01 Mar 2021 |
Technichal Pre-Qualification | 01 Mar 2021 |
Price bid opening | 01 Mar 2021 |
NA | 16 Jul 2021 |
---|---|
Workorder Date | 29 Apr 2021 |
Nattika Project Dn EE |
Date: 09/06/2023 |
Work in progress | 91% Completed
79 FHTC to be completed. Pipe line extension exceeded than the scheduled agreement quantity. To complete balance 79 connection more extension to be needed. So request for considering AS as final bill submitted. Bill under scruitiny under division .
Nattika Project Dn EE |
Date: 08/06/2023 |
Work in progress | 91% Completed
79 FHTC to be completed. Pipe line extension exceeded than the scheduled agreement quantity. To complete balance 79 connection more extension to be needed. So request for considering AS as final bill submitted. Bill under scruitiny under division .