Project | Jal Jeevan Mission (JJM)-5th SLSSC – Kolazhy Grama Panchayath - Thrissur District-Providing Distribution Lines and 175 FHTCs near KWA Pump house, Pamboor and PWD road restoration- Package I - Part A |
---|---|
Project Code | TCRJJM022213577P1 |
Type | Package |
Main Project | Jal Jeevan Mission (JJM)-5th SLSSC – Kolazhy Grama Panchayath - Thrissur District-Providing Distribution Lines and FHTCs |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Jal Jeevan Mission (JJM)-5th SLSSC – Kolazhy Grama Panchayath - Thrissur District-Providing Distribution Lines and 175 FHTCs near KWA Pump house, Pamboor and PWD road restoration- Package I - Part A |
Status | On-going |
District | Thrissur |
Executing Office | Thrissur WW Sn 1 |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 10000000 |
TS Number | WRD/KWA-CE(CR)/EST_TS/14182/2022_26_14_13 Dated: 09-01-2023 |
Technical specification | Providing Distribution Lines and 175 FHTCs. |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 31/01/2023 |
---|---|
Scheduled date of Completion as per agreement | 30 Jan 2024 |
Expected date of Completion | 29/02/2024 |
TS Date | 09 Jan 2023 |
---|---|
Estimate Approval | 09 Jan 2023 |
NIT Approval | 10 Jan 2023 |
Tender Closing | 17 Jan 2023 |
Technichal Pre-Qualification | 17 Jan 2023 |
Price bid opening | 18 Jan 2023 |
Workorder Date | 31 Jan 2023 |
---|---|
NA | 09 Feb 2023 |
Thrissur WW Sn - AE 1 |
Date: 25/06/2024 |
Work has been completed | 100% Completed
Work completed, bill submitted..
Thrissur PH Dn EE |
Date: 15/02/2024 |
Work has been completed | 100% Completed
Work completed, bill under preparation..