- Home
- KIIFB-UTILITY SHIFTING-Punnakkadavu- Put...
KIIFB-UTILITY SHIFTING-Punnakkadavu- Puthiyapuzhakakra- Ezhlimala Railway station -Ezhilode Road-Pipeline Work
| Project |
KIIFB-UTILITY SHIFTING-Punnakkadavu- Puthiyapuzhakakra- Ezhlimala Railway station -Ezhilode Road-Pipeline Work |
| Project Code |
KNRKIIFB102518096 |
| Type |
Main project |
| Funding Agency |
KIIFB |
| Category |
Deposit Work |
| Type of scheme |
Water Supply |
| Scheme |
KIIFB |
| Description |
KIIFB-UTILITY SHIFTING-Punnakkadavu- Puthiyapuzhakakra- Ezhlimala Railway station -Ezhilode Road-Pipeline Work |
| Status |
On-going |
| District |
Kannur |
| Executing Office |
Pilathra WS Sn |
| AS Amount (Rs) |
110000
|
| AS Number |
EE/KRFB/KNR/AEEII/J13(B)/2021 |
| TS Amount (Rs) |
100000 |
| TS Number |
WRD/KWA-CE(NR)/EST_TS/30655/2024_26_1_1 |
| Total Bill Submitted (Rs) |
|
| Total Bill Paid (Rs) |
|
| Population Benefitted |
|
| Capacity in MLD |
|
| Actual Project Completion Date |
Date is not specified |
| Coverage |
|
Packages
| No. |
Project Name |
Location |
View |
| 1 |
KIIFB-UTILITY SHIFTING-Punnakkadavu- Puthiyapuzhakakra- Ezhlimala Railway station -Ezhilode Road-Pipeline Work |
Pilathra WS Sn |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 14 Jan 2026 |
Tender opened on 30.12.2025 |
Thaliparamba WS Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
| Date of start of Project |
Date is not specified |
| Scheduled date of Completion of the Project |
Date is not specified |
| Expected date of Completion |
Date is not specified |
Processing Dates
| AS Date |
31 Oct 2025 |
| TS Date |
07 Nov 2025 |