AMRUT -Providing Sewer trunk from Kazhakoottam area toPumping station of I Block through the bank ofThettiyar Thodu - Collection and Conveyance system. and pumping station, pumps and electricalinstallation, Pumping mains (Block I)-( 5 packages)

Project AMRUT -Providing Sewer trunk from Kazhakoottam area toPumping station of I Block through the bank ofThettiyar Thodu - Collection and Conveyance system. and pumping station, pumps and electricalinstallation, Pumping mains (Block I)-( 5 packages)
Project Code TVMAMRUT0217702
Type Main project
Funding Agency AMRUT
Category AMRUT
Type of scheme Sewerage
Scheme AMRUT
Description The above work has 4 packages 1.pumping main from Kulathoor pumping station to Arasumood 2.Construction of collecting well 3.Installation of Pumps,Transformer etc. 4.Laying of transmission main
Status On-going
District Thiruvananthapuram
Executing Office Trivandrum Project Dn
AS Amount (Rs) 123500000
AS Number GO(Rt)No.803/2021/LSGD
TS Amount (Rs) 56000000
TS Number TS/2019-2020/2018/5155
Total Bill Submitted (Rs) 15910487
Total Bill Paid (Rs) 15910487
Population Benefitted 3000
Capacity in MLD 2.56
Actual Project Completion Date 30 Sep 2022
Coverage Attipra,Poundkadavu,Kulathoor wards
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Package-1-Pumping main from kulathoor proposed pumping station to arasumoodu Trivandrum Project Dn
2 Package -2. Construction of pumping station at Kulathoor Trivandrum Project Dn
3 Package 3 - (Part 1) Laying Sewer trunk along thettiyar thode (Through Kallingal Road) Trivandrum Project Dn
4 Package 3 - (Part 2) Laying Sewer trunk along thettiyar thode- Conveying & Laying 500 mm dia HDPE pipe from Kulathoor Jn. to Pumping Station at Kulathoor through HDD method Trivandrum Project Dn
5 Package-4. Supplying,errection of pumpsets, Transformer and electrical accessories in the kulathoor pumping station Trivandrum Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
13 May 2024 2024 Concreting and bottom plugging of both wells & grit chamber completed. Concreting of MH near grit chamber completed. Pump house building and Generator room completed, Compound wall completed, Gantry beams concrete work completed. Inside plastering of Well No.1 & Well No.2 has been completed. Interconnection with Wells and grit chamber and grit chamber to lateral manhole has to be done. Thiruvananthapuram Project AE9
08 May 2024 2024 Concreting and bottom plugging of both wells & grit chamber completed. Concreting of MH near grit chamber completed. Pump house building and Generator room completed, Compound wall completed, Gantry beams concrete work completed. Inside plastering of Well No.1 & Well No.2 has been completed. Interconnection with Wells and grit chamber and grit chamber to lateral manhole has to be done. Thiruvananthapuram Project AE9
04 May 2024 Concreting and bottom plugging of both wells & grit chamber completed. Concreting of MH near grit chamber completed. Pump house building and Generator room completed, Compound wall completed, Gantry beams concrete work completed. Inside plastering of Well No.1 & Well No.2 has been completed. Interconnection with Wells and grit chamber and grit chamber to lateral manhole has to be done. Thiruvananthapuram Project AE9
30 Apr 2024 Concreting and bottom plugging of both wells & grit chamber completed. Concreting of MH near grit chamber completed. Pump house building and Generator room completed, Compound wall completed, Gantry beams concrete work completed. Inside plastering of Well No.1 & Well No.2 has been completed. Interconnection with Wells and grit chamber and grit chamber to lateral manhole has to be done. Thiruvananthapuram Project AE9
27 Apr 2024 Concreting and bottom plugging of both wells & grit chamber completed. Concreting of MH near grit chamber completed. Pump house building and Generator room completed, Compound wall completed, Gantry beams concrete work completed. Inside plastering of Well No.1 & Well No.2 has been completed. Interconnection with Wells and grit chamber and grit chamber to lateral manhole has to be done. Thiruvananthapuram Project AE9

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 06/03/2018
Scheduled date of Completion of the Project 24 Feb 2022
Expected date of Completion 31/05/2024

Processing Dates

AS Date 30 Mar 2021
TS Date 06 Mar 2018

Other details