AMRUT -Providing Sewer trunk from Kazhakoottam area toPumping station of I Block through the bank ofThettiyar Thodu - Collection and Conveyance system. and pumping station, pumps and electricalinstallation, Pumping mains (Block I)-( 5 packages)
Project |
AMRUT -Providing Sewer trunk from Kazhakoottam area toPumping station of I Block through the bank ofThettiyar Thodu - Collection and Conveyance system. and pumping station, pumps and electricalinstallation, Pumping mains (Block I)-( 5 packages) |
Project Code |
TVMAMRUT0217702 |
Type |
Main project |
Funding Agency |
AMRUT |
Category |
AMRUT |
Type of scheme |
Sewerage |
Scheme |
AMRUT |
Description |
The above work has 4 packages
1.pumping main from Kulathoor pumping station to Arasumood
2.Construction of collecting well
3.Installation of Pumps,Transformer etc.
4.Laying of transmission main |
Status |
On-going |
District |
Thiruvananthapuram |
Executing Office |
Trivandrum Project Dn |
AS Amount (Rs) |
123500000
|
AS Number |
GO(Rt)No.803/2021/LSGD |
TS Amount (Rs) |
56000000 |
TS Number |
TS/2019-2020/2018/5155 |
Total Bill Submitted (Rs) |
15910487 |
Total Bill Paid (Rs) |
15910487 |
Population Benefitted |
3000 |
Capacity in MLD |
2.56 |
Actual Project Completion Date |
30 Sep 2022 |
Coverage |
Attipra,Poundkadavu,Kulathoor wards |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Package-1-Pumping main from kulathoor proposed pumping station to arasumoodu |
Trivandrum Project Dn |
|
2 |
Package -2. Construction of pumping station at Kulathoor |
Trivandrum Project Dn |
|
3 |
Package 3 - (Part 1) Laying Sewer trunk along thettiyar thode (Through Kallingal Road) |
Trivandrum Project Dn |
|
4 |
Package 3 - (Part 2) Laying Sewer trunk along thettiyar thode- Conveying & Laying 500 mm dia HDPE pipe from Kulathoor Jn. to Pumping Station at Kulathoor through HDD method |
Trivandrum Project Dn |
|
5 |
Package-4. Supplying,errection of pumpsets, Transformer and electrical accessories in the kulathoor pumping station |
Trivandrum Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
13 May 2024 |
2024 Concreting and bottom plugging of both wells & grit chamber completed. Concreting of MH near grit chamber completed. Pump house building and Generator room completed, Compound wall completed, Gantry beams concrete work completed. Inside plastering of Well No.1 & Well No.2 has been completed. Interconnection with Wells and grit chamber and grit chamber to lateral manhole has to be done. |
Thiruvananthapuram Project AE9 |
|
08 May 2024 |
2024 Concreting and bottom plugging of both wells & grit chamber completed. Concreting of MH near grit chamber completed. Pump house building and Generator room completed, Compound wall completed, Gantry beams concrete work completed. Inside plastering of Well No.1 & Well No.2 has been completed. Interconnection with Wells and grit chamber and grit chamber to lateral manhole has to be done. |
Thiruvananthapuram Project AE9 |
|
04 May 2024 |
Concreting and bottom plugging of both wells & grit chamber completed. Concreting of MH near grit chamber completed. Pump house building and Generator room completed, Compound wall completed, Gantry beams concrete work completed. Inside plastering of Well No.1 & Well No.2 has been completed. Interconnection with Wells and grit chamber and grit chamber to lateral manhole has to be done. |
Thiruvananthapuram Project AE9 |
|
30 Apr 2024 |
Concreting and bottom plugging of both wells & grit chamber completed. Concreting of MH near grit chamber completed. Pump house building and Generator room completed, Compound wall completed, Gantry beams concrete work completed. Inside plastering of Well No.1 & Well No.2 has been completed. Interconnection with Wells and grit chamber and grit chamber to lateral manhole has to be done. |
Thiruvananthapuram Project AE9 |
|
27 Apr 2024 |
Concreting and bottom plugging of both wells & grit chamber completed. Concreting of MH near grit chamber completed. Pump house building and Generator room completed, Compound wall completed, Gantry beams concrete work completed. Inside plastering of Well No.1 & Well No.2 has been completed. Interconnection with Wells and grit chamber and grit chamber to lateral manhole has to be done. |
Thiruvananthapuram Project AE9 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
06/03/2018 |
Scheduled date of Completion of the Project |
24 Feb 2022 |
Expected date of Completion |
31/05/2024 |
Processing Dates
AS Date |
30 Mar 2021 |
TS Date |
06 Mar 2018 |