Deposit work - Kollam district panchayath - Providing water supply to Kattoottil colony in Chadayamangalam grama Panchayath, Supply and erection of pump sets, Repacking of infiltration gallery, De-silting of well, Renovation of pump house etc at Mulayam pump house
| Project |
Deposit work - Kollam district panchayath - Providing water supply to Kattoottil colony in Chadayamangalam grama Panchayath, Supply and erection of pump sets, Repacking of infiltration gallery, De-silting of well, Renovation of pump house etc at Mulayam pump house |
| Project Code |
KLMDEPO022210141P1 |
| Type |
Package |
| Main Project |
Deposit work - Kollam district panchayath - Providing water supply to Kattoottil colony in Chadayamangalam grama Panchayath, Supply and erection of pump sets, Repacking of infiltration gallery, De-silting of well, Renovation of pump house etc at Mulayam pump house
|
| Funding Agency |
DEPO |
| Category |
Deposit Work |
| Type of scheme |
Water Supply |
| Scheme |
DEPO |
| Description |
Providing water supply to Kattoottil colony in Chadayamangalam grama Panchayath, Supply and erection of pump sets, Repacking of infiltration gallery, De-silting of well, Renovation of pump house etc at Mulayam pump house |
| Status |
On-going |
| District |
Kollam |
| Executing Office |
Kadakkal PH Sn |
| Agreement Number |
|
| Agreement Date |
|
| TS Amount (Rs) |
9985000 |
| TS Number |
TS/2021-2022/2021/41788 Dated: 22-02-2022 |
| Technical specification |
Kattottil colony area in Chadayamangalam Panchayath |
| Contractor |
Chandramohan C (Mob: 8078048864) |
No project review have been added to this project
|
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
| Date of start of Package |
02/04/2022 |
| Scheduled date of Completion as per agreement |
28 Jul 2022 |
| Expected date of Completion |
01/07/2022 |
Processing Dates
| TS Date |
22 Feb 2022 |
| Estimate Approval |
22 Feb 2022 |
| NIT Approval |
22 Feb 2022 |
| Tender Closing |
10 Mar 2022 |
| Technichal Pre-Qualification |
10 Mar 2022 |
| Price bid opening |
11 Mar 2022 |
Approval Dates
| Workorder Date |
28 Mar 2022 |
| NA |
28 Mar 2022 |
Other details
| Project Schedule |
View |
| Project Components |
View |
| Project Officers |
View |
| Kottarakkara PH Dn EE |
| Date: 05/07/2023 |
Work has been completed | 100% Completed
Work Completed.
| Kadakkal PH Sn - AE |
| Date: 12/06/2023 |
Work in progress | 97% Completed
Last phase pipe line works ongoing
.