Jaljeevanmission 2020-21 Phase II - Mulakkulam Panchayat. Providing FHTC in various wards by retrofitting/Augmenting/ extending the existing distribution system coming under the jurisdiction of P H Division, Kaduthuruthy

Project Jaljeevanmission 2020-21 Phase II - Mulakkulam Panchayat. Providing FHTC in various wards by retrofitting/Augmenting/ extending the existing distribution system coming under the jurisdiction of P H Division, Kaduthuruthy
Project Code KTMJJM12206543
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description providing 2300 FHTC s in various wards of Mulakulam Panchayath under JJM Phase II. This panchayath have a population of 28836 and spreads over an area of 26.15Sq.Km.
Status On-going
District Kottayam
Executing Office Kaduthuruthy PH Dn
AS Amount (Rs) 60084000
AS Number GO (Rt) No.777/2020/WRD
TS Amount (Rs) 59932000
TS Number TS/2020-2021/2020/28330
Total Bill Submitted (Rs) 10074000
Total Bill Paid (Rs) 10074000
Population Benefitted 28836
Capacity in MLD 0.20
Actual Project Completion Date 31 Mar 2022
Coverage providing 2300 FHTC s in various wards of Mulakulam Panchayath under JJM Phase II. This panchayath have a population of 28836 and spreads over an area of 26.15Sq.Km.
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Jaljeevanmission 2020-21 Phase II - Mulakkulam Panchayat. Providing FHTC in various wards by retrofitting/Augmenting/ extending the existing distribution system coming under the jurisdiction of P H Division, Kaduthuruthy Peruva Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
28 Jun 2024 Bill under preparation Kaduthuruthy Dn EE
27 Jun 2024 Bill under preparation Kaduthuruthy Dn EE
26 Jun 2024 Bill under preparation Kaduthuruthy Dn EE
25 Jun 2024 Bill under preparation Kaduthuruthy Dn EE
24 Jun 2024 Bill under preparation Kaduthuruthy Dn EE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 23/04/2021
Scheduled date of Completion of the Project 22 Aug 2021
Expected date of Completion 20/08/2022

Processing Dates

AS Date 24 Dec 2020
TS Date 10 Jan 2021

Other details

Project Officers View