JJM-Additional proposals for the works during 2021-2022 Ottasekharamangalam GP - CWSS to Parassala, Marukil, Maranallur and Adj. villages - Phase III - Augmentation of Distribution network and providing remaining FHTCs in Ottasekharamangalam GP.

Project JJM-Additional proposals for the works during 2021-2022 Ottasekharamangalam GP - CWSS to Parassala, Marukil, Maranallur and Adj. villages - Phase III - Augmentation of Distribution network and providing remaining FHTCs in Ottasekharamangalam GP.
Project Code TVMJJM022213274P1
Type Package
Main Project JJM-Additional proposals for the works during 2021-2022 Ottasekharamangalam GP - CWSS to Parassala, Marukil, Maranallur and Adj. villages - Phase III - Augmentation of Distribution network and providing remaining FHTCs in Ottasekharamangalam GP.
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM-Additional proposals for the works during 2021-2022 Ottasekharamangalam GP - CWSS to Parassala, Marukil, Maranallur and Adj. villages - Phase III - Augmentation of Distribution network and providing remaining FHTCs in Ottasekharamangalam GP.
Status On-going
District Thiruvananthapuram
Executing Office Kattakada WS Sn
Agreement Number
Agreement Date
TS Amount (Rs) 60900000
TS Number TS/2022 2023/2021/27045
Technical specification JJM-Additional proposals for the works during 2021-2022 Ottasekharamangalam GP - CWSS to Parassala, Marukil, Maranallur and Adj. villages - Phase III - Augmentation of Distribution network and providing remaining FHTCs in Ottasekharamangalam GP.

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 13/10/2022
Scheduled date of Completion as per agreement 13 Feb 2023
Expected date of Completion 10/02/2023

Processing Dates

TS Date 23 Aug 2022
Estimate Approval 23 Feb 2022
NIT Approval 23 Feb 2022
Tender Closing 13 Sep 2022
Technichal Pre-Qualification 30 Sep 2022
Price bid opening 30 Sep 2022

Approval Dates

Workorder Date 13 Oct 2022
NA 28 Oct 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Neyyattinkara WS Dn EE
Date: 28/06/2024

Work in progress | 93% Completed

FHTC conversion is Prossing.

Neyyattinkara WS Dn EE
Date: 24/06/2024

Work in progress | 91% Completed

FHTC conversion is Prossing.