Jal jeevan Mission(JJM)-Kasaragod District-WSS to ajanur,Pallikara,Uduma,Pullur periya Panchayath-Package-4-Construction of 10LL capacity OHSR &:Laying distribution system and providing FHTCs in Pallikara Panchayath(Part)-General work

Project Jal jeevan Mission(JJM)-Kasaragod District-WSS to ajanur,Pallikara,Uduma,Pullur periya Panchayath-Package-4-Construction of 10LL capacity OHSR &:Laying distribution system and providing FHTCs in Pallikara Panchayath(Part)-General work
Project Code KGDJJM022215360
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal jeevan Mission(JJM)-Kasaragod District-WSS to ajanur,Pallikara,Uduma,Pullur periya Panchayath-Package-4-Construction of 10LL capacity OHSR &:Laying distribution system and providing FHTCs in Pallikara Panchayath(Part)-General work
Status On-going
District Kasaragod
Executing Office Kasargod PH Dn
AS Amount (Rs) 2688272000
AS Number G.O(Rt)no.489/2021/WRD
TS Amount (Rs) 254700000
TS Number WRD/KWA-CE(NR)/EST_TS/669/2022_5_5_4
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date Date is not specified
Coverage

Packages

No. Project Name Location View
1 Jal jeevan Mission(JJM)-Kasaragod District-WSS to ajanur,Pallikara,Uduma,Pullur periya Panchayath-Package-4-Construction of 10LL capacity OHSR &:Laying distribution system and providing FHTCs in Pallikara Panchayath(Part)-General work Kanhangad PH Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
13 May 2024 work in progress Kanhangad PH Sn AE
06 May 2024 work in progress Kanhangad PH Sn AE
30 Apr 2024 work in progress Kanhangad PH Sn AE
22 Apr 2024 work in progress Kanhangad PH Sn AE
18 Apr 2024 work in progress Kanhangad PH Sn AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 28/09/2023
Scheduled date of Completion of the Project 27 Jun 2024
Expected date of Completion 27/06/2024

Processing Dates

AS Date 23 Feb 2022
TS Date 26 Apr 2023

Other details

Project Officers View