Project | KIIFB-WRD005-129-001 uwss to manjeri -replacing old aged Ac pipes |
---|---|
Project Code | MLPKIIFB0418590P1 |
Type | Package |
Main Project | WRD005-129-Project 4 - UWSS to Manjeri- Replacing old aged AC pipes with DI pipes of Manjeri Municipality |
Funding Agency | KIIFB |
Category | KIIFB |
Type of scheme | Water Supply |
Scheme | KIIFB |
Description | REPLACING EXISTING AC PIPE WIT DI AND PROVIDIG RIDER MAIN ETC 600mm DI 350mtr 500mm DI 1470mtr 450mm DI 510mtr 400mm DI 420mtr 300mm DI 5740 mtr 250mm DI 2285 mtr 160mm PVC 22255 mt with road restoration |
Status | On-going |
District | Malappuram |
Executing Office | Malappuram Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 166400000 |
TS Number | 1021/2020-21 |
Technical specification | REPLACING EXISTING AC PIPE WIT DI AND PROVIDIG RIDER MAIN ETC 600mm DI 350mtr 500mm DI 1470mtr 450mm DI 510mtr 400mm DI 420mtr 300mm DI 5740 mtr 250mm DI 2285 mtr 160mm PVC 22255 mt |
Issue date | Solved On | Action Taken On | Category | Description | Comments | Issue Status |
---|---|---|---|---|---|---|
15 Dec 2021 | Pending | Pending | Road Cut Related Risk | PWD road cutting permission 1. manjeri - olipuzha road 2. kozhikode nilambur road 3. malappuram manjeri road 4. cherani mangalaseri road | No comments available. | Pending |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 01/12/2020 |
---|---|
Scheduled date of Completion as per agreement | 15 Oct 2021 |
Expected date of Completion | 28/02/2023 |
TS Date | 14 May 2020 |
---|---|
Estimate Approval | 14 May 2020 |
NIT Approval | 09 Jun 2020 |
Tender Closing | 29 Jul 2020 |
Technichal Pre-Qualification | 02 Sep 2020 |
Price bid opening | 16 Sep 2020 |
Workorder Date | 16 Oct 2020 |
---|---|
NA | 27 Oct 2020 |
Malapuram Proj Dn AE 4 |
Date: 04/05/2024 |
Work in progress | 93% Completed
Pipe line work completed for 24Km and balance pending for non getting permission from PWD. Road restoration work for the completed portion BM & BC work is completed .
Malapuram Proj Dn AE 4 |
Date: 03/05/2024 |
Work in progress | 93% Completed
Pipe line work completed for 24Km and balance pending for non getting permission from PWD. Road restoration work for the completed portion BM & BC work is completed .