Jal Jeevan Mission (JJM)-Kottappady GP-Supply Erection and commissioning of CF pump sets having discharge of 24LPS against total head of 96m to CWPH at Pezhad Pump House in Kottappady Panchayath-General Civil Work
Project |
Jal Jeevan Mission (JJM)-Kottappady GP-Supply Erection and commissioning of CF pump sets having discharge of 24LPS against total head of 96m to CWPH at Pezhad Pump House in Kottappady Panchayath-General Civil Work |
Project Code |
EKMJJM082015598 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Jal Jeevan Mission (JJM)-Kottappady GP-Supply Erection and commissioning of CF pump sets having discharge of 24LPS against total head of 96m to CWPH at Pezhad Pump House in Kottappady Panchayath-General Civil Work |
Status |
On-going |
District |
Ernakulam |
Executing Office |
Muvattupuzha PH Dn |
AS Amount (Rs) |
36400000
|
AS Number |
G.O(Rt)No.541/2020/WRD dated 21/08/2020 |
TS Amount (Rs) |
4130053 |
TS Number |
17776/2023-2024 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
100 |
Capacity in MLD |
0.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Supply Erection and commissioning of CF pump sets having discharge of 24LPS against total head of 96m to CWPH at Pezhad Pump House in Kottappady Panchayath |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission (JJM)-Kottappady GP-Supply Erection and commissioning of CF pump sets having discharge of 24LPS against total head of 96m to CWPH at Pezhad Pump House in Kottappady Panchayath-General Civil Work |
Kothamangalam Sn 2 |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
25 Jun 2024 |
work in progress |
Kothamangalam PH Sn 2 - AE |
|
20 Apr 2024 |
Work in progress |
Muvattupuzha PH Dn EE |
|
02 Apr 2024 |
ongoing |
Kothamangalam PH Sn 2 - AE |
|
20 Mar 2024 |
work started |
Kothamangalam PH Sn 2 - AE |
|
16 Mar 2024 |
work started |
Kothamangalam PH Sn 2 - AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
12/12/2023 |
Scheduled date of Completion of the Project |
11 Apr 2024 |
Expected date of Completion |
11/04/2024 |
Processing Dates
AS Date |
21 Aug 2020 |
TS Date |
31 Oct 2023 |