Automation of pump houses of Kerala Water Authority- Implementation of Phase 1 (Stage 1 & 2) under Rebuild Kerala Initiative

Project Automation of pump houses of Kerala Water Authority- Implementation of Phase 1 (Stage 1 & 2) under Rebuild Kerala Initiative
Project Code TVMRKI03229327
Type Main project
Funding Agency RKI
Category RKI
Type of scheme Water Supply
Scheme 5475-00-115-94-05
Description KWA has 2430 pumps out of which 1039 is submersible pumps, 416 is VT pumps, 850 centrifugal pumps and 125 other types. Of the above 608 submersible pumps are automated. automation of 29 pumps are ongoing. This project is intended to automate the remaining 402 submersible pumps and 416 Nos Vertical Turbine Pumps.
Status On-going
District Thiruvananthapuram
Executing Office Head Office
AS Amount (Rs) 114200000
AS Number G.O.(Rt)No.74/2022/P&EA
TS Amount (Rs) 114200000
TS Number 12345
Total Bill Submitted (Rs) 11600000
Total Bill Paid (Rs) 13000000
Population Benefitted 1000000
Capacity in MLD 1000.00
Actual Project Completion Date Date is not specified
Coverage All Division
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Automation RKI-Phase 1 Stage 1 -part-Reserve control starter module Head Office
2 RKI Automation of Submersible Pumps 348 nos -Phase 1 Stage 1-part Head Office
3 RKI Automation-Phase 1-stage 1 part- Post automation support activities-Disinfection arrangements Head Office
4 RKI Automation-Surveillance mechanism for automated pumping stations Head Office

Overall Project Status

Status Date Overall Project Status Project Officer Contact
18 Nov 2022 Review made for speedy completion Operation AEE
27 Aug 2022 Ongoing achieved 75% Operations AE 3
04 Aug 2022 Ongoing Operations AE 3
11 Apr 2022 Phase 1 stage 1 AS accorded vide proceedings dated 15/3, 23/03,30/3,04/04/2022 Operations AE 3

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 20/04/2022
Scheduled date of Completion of the Project 31 Oct 2022
Expected date of Completion 31/05/2023

Processing Dates

AS Date 03 Mar 2022
TS Date 01 Jun 2022

Other details

Project Officers View