Automation of pump houses of Kerala Water Authority- Implementation of Phase 1 (Stage 1 & 2) under Rebuild Kerala Initiative
Project |
Automation of pump houses of Kerala Water Authority- Implementation of Phase 1 (Stage 1 & 2) under Rebuild Kerala Initiative |
Project Code |
TVMRKI03229327 |
Type |
Main project |
Funding Agency |
RKI |
Category |
RKI |
Type of scheme |
Water Supply |
Scheme |
5475-00-115-94-05 |
Description |
KWA has 2430 pumps out of which 1039 is submersible pumps, 416 is VT pumps, 850 centrifugal pumps and 125 other types. Of the above 608 submersible pumps are automated. automation of 29 pumps are ongoing. This project is intended to automate the remaining 402 submersible pumps and 416 Nos Vertical Turbine Pumps. |
Status |
On-going |
District |
Thiruvananthapuram |
Executing Office |
Head Office |
AS Amount (Rs) |
114200000
|
AS Number |
G.O.(Rt)No.74/2022/P&EA |
TS Amount (Rs) |
114200000 |
TS Number |
12345 |
Total Bill Submitted (Rs) |
11600000 |
Total Bill Paid (Rs) |
13000000 |
Population Benefitted |
1000000 |
Capacity in MLD |
1000.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
All Division |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Automation RKI-Phase 1 Stage 1 -part-Reserve control starter module |
Head Office |
|
2 |
RKI Automation of Submersible Pumps 348 nos -Phase 1 Stage 1-part |
Head Office |
|
3 |
RKI Automation-Phase 1-stage 1 part- Post automation support activities-Disinfection arrangements |
Head Office |
|
4 |
RKI Automation-Surveillance mechanism for automated pumping stations |
Head Office |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
18 Nov 2022 |
Review made for speedy completion |
Operation AEE |
|
27 Aug 2022 |
Ongoing achieved 75% |
Operations AE 3 |
|
04 Aug 2022 |
Ongoing |
Operations AE 3 |
|
11 Apr 2022 |
Phase 1 stage 1 AS accorded vide proceedings dated 15/3, 23/03,30/3,04/04/2022 |
Operations AE 3 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
20/04/2022 |
Scheduled date of Completion of the Project |
31 Oct 2022 |
Expected date of Completion |
31/05/2023 |
Processing Dates
AS Date |
03 Mar 2022 |
TS Date |
01 Jun 2022 |