JJM-WSS to Koratty and Kadukutty Panchayath in Thrissur district providing 900 FHTC's and streetmain extension at Koratty Panchayath ongoing (MVS), Part II

Project JJM-WSS to Koratty and Kadukutty Panchayath in Thrissur district providing 900 FHTC's and streetmain extension at Koratty Panchayath ongoing (MVS), Part II
Project Code TCRJJM08207125P11
Type Package
Main Project JJM-WSS to Koratty and Kadukutty Panchayath in Thrissur district providing FHTC and streetmain extension at Koratty Panchayath ongoing (MVS)
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM-WSS to Koratty and Kadukutty Panchayath in Thrissur district providing 900 FHTC's and streetmain extension at Koratty Panchayath ongoing (MVS), Part II
Status On-going
District Thrissur
Executing Office Nattika Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 409100000
TS Number TS/2020-21/2020/22628
Technical specification providing 900 FHTC's and streetmain extension at Koratty Panchayath ongoing (MVS)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 13/07/2021
Scheduled date of Completion as per agreement 12 Jan 2022
Expected date of Completion Date is not specified

Processing Dates

TS Date 24 Oct 2020
Estimate Approval 24 Oct 2020
NIT Approval 24 Oct 2020
Tender Closing 01 Mar 2021
Technichal Pre-Qualification 24 Oct 2020
Price bid opening 03 Mar 2021

Approval Dates

Workorder Date 13 Jul 2021
NA 13 Sep 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Nattika Project Dn EE
Date: 14/06/2023

Work in progress | 26% Completed

79 FHTC to be completed. Pipe line extension exceeded than the scheduled agreement quantity. To complete balance 79 connection more extension to be needed. So request for considering AS as final bill submitted. Bill under scruitiny under division .

Nattika Project Dn EE
Date: 13/06/2023

Work in progress | 26% Completed

79 FHTC to be completed. Pipe line extension exceeded than the scheduled agreement quantity. To complete balance 79 connection more extension to be needed. So request for considering AS as final bill submitted. Bill under scruitiny under division .