| Project | AMRUT-2.0- Phase-1-Changanacherry Municipality-Laying Conveyance mains and Distribution pipe lines and providing 200FHTCs including road restoration work. |
|---|---|
| Project Code | KTMAMRUT112215414P1 |
| Type | Package |
| Main Project | AMRUT-2.0- Phase-1-Changanacherry Municipality-Laying Conveyance mains and Distribution pipe lines and providing 200FHTCs including road restoration work. |
| Funding Agency | AMRUT |
| Category | AMRUT 2 |
| Type of scheme | Water Supply |
| Scheme | AMRUT |
| Description | AMRUT-2.0- Phase-1-Changanacherry Municipality-Laying Conveyance mains and Distribution pipe lines and providing 200FHTCs including road restoration work. |
| Status | On-going |
| District | Kottayam |
| Executing Office | Changanassery Sn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 95470000 |
| TS Number | WRD/KWA-CE(SR)/EST_TS/19335/2023_26_1_1 |
| Technical specification | |
| Contractor | SanilKumar (Mob: 9447234871) |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 24/11/2022 |
|---|---|
| Scheduled date of Completion as per agreement | 21 Sep 2024 |
| Expected date of Completion | 21/09/2024 |
| TS Date | 16 Sep 2023 |
|---|---|
| Estimate Approval | 16 Sep 2023 |
| NIT Approval | 16 Sep 2023 |
| Tender Closing | 14 Nov 2023 |
| Technichal Pre-Qualification | 29 Nov 2023 |
| Price bid opening | 29 Nov 2023 |
| Workorder Date | 13 Dec 2023 |
|---|---|
| NA | 22 Dec 2023 |
| Changanaserry PH Sn - AE |
| Date: 31/08/2026 |
Work in progress | 71% Completed
Pipe laying work is in progress. 350 mm DI pipe :- 2430 m, 200 mm DI pipe :- 1412.5 m and 160 mm PVC pipe: 14370 m laid. Road restoration work ongoing. 1. Construction of the road base by providing GSB - 4942m, 2. Laying old cement concrete interlocking paver blocks - 2100 m, 3. Concrete Road Restoration - 920 m, 4. Tar road restoration- 3649.3 m.
| Changanaserry PH Sn - AE |
| Date: 09/07/2026 |
Work in progress | 71% Completed
Pipe laying work is in progress. 350 mm DI pipe :- 1400 m, 200 mm DI pipe :- 1455.87 m and 160 mm PVC pipe: 11645.50 m laid. Road restoration work ongoing. 1. Construction of the road base by providing GSB - 4942m, 2. Laying old cement concrete interlocking paver blocks - 2100 m, 3. Concrete Road Restoration - 920 m, 4. Tar road restoration- 3649.3 m.