AMRUT-2.0- Phase-1-Changanacherry Municipality-Laying Conveyance mains and Distribution pipe lines and providing 200FHTCs including road restoration work.

Project AMRUT-2.0- Phase-1-Changanacherry Municipality-Laying Conveyance mains and Distribution pipe lines and providing 200FHTCs including road restoration work.
Project Code KTMAMRUT112215414P1
Type Package
Main Project AMRUT-2.0- Phase-1-Changanacherry Municipality-Laying Conveyance mains and Distribution pipe lines and providing 200FHTCs including road restoration work.
Funding Agency AMRUT
Category AMRUT 2
Type of scheme Water Supply
Scheme AMRUT
Description AMRUT-2.0- Phase-1-Changanacherry Municipality-Laying Conveyance mains and Distribution pipe lines and providing 200FHTCs including road restoration work.
Status On-going
District Kottayam
Executing Office Changanassery Sn
Agreement Number
Agreement Date
TS Amount (Rs) 95470000
TS Number WRD/KWA-CE(SR)/EST_TS/19335/2023_26_1_1
Technical specification
Contractor SanilKumar (Mob: 9447234871)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 24/11/2022
Scheduled date of Completion as per agreement 21 Sep 2024
Expected date of Completion 21/09/2024

Processing Dates

TS Date 16 Sep 2023
Estimate Approval 16 Sep 2023
NIT Approval 16 Sep 2023
Tender Closing 14 Nov 2023
Technichal Pre-Qualification 29 Nov 2023
Price bid opening 29 Nov 2023

Approval Dates

Workorder Date 13 Dec 2023
NA 22 Dec 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Changanaserry PH Sn - AE
Date: 31/08/2026

Work in progress | 71% Completed

Pipe laying work is in progress. 350 mm DI pipe :- 2430 m, 200 mm DI pipe :- 1412.5 m and 160 mm PVC pipe: 14370 m laid. Road restoration work ongoing. 1. Construction of the road base by providing GSB - 4942m, 2. Laying old cement concrete interlocking paver blocks - 2100 m, 3. Concrete Road Restoration - 920 m, 4. Tar road restoration- 3649.3 m.

Changanaserry PH Sn - AE
Date: 09/07/2026

Work in progress | 71% Completed

Pipe laying work is in progress. 350 mm DI pipe :- 1400 m, 200 mm DI pipe :- 1455.87 m and 160 mm PVC pipe: 11645.50 m laid. Road restoration work ongoing. 1. Construction of the road base by providing GSB - 4942m, 2. Laying old cement concrete interlocking paver blocks - 2100 m, 3. Concrete Road Restoration - 920 m, 4. Tar road restoration- 3649.3 m.