Jal Jeevan Mission -SUPPLYING AND LAYING OF 13KM PIPE LINE NETWORK-JJM-SUPPLY AND LAYING OF 13KM PIPE LINE NETWORK FOR NOORANAD,PALAMEL,CHUNAKKARA AND THAMARAKULAM GRAMAPANCHAYATH-Pipeline Work-1-Additional supply of 90mm and 110mm, 8kg/cm2 PVC pipe lines for new house connections

Project Jal Jeevan Mission -SUPPLYING AND LAYING OF 13KM PIPE LINE NETWORK-JJM-SUPPLY AND LAYING OF 13KM PIPE LINE NETWORK FOR NOORANAD,PALAMEL,CHUNAKKARA AND THAMARAKULAM GRAMAPANCHAYATH-Pipeline Work-1-Additional supply of 90mm and 110mm, 8kg/cm2 PVC pipe lines for new house connections
Project Code ALPJJM08207717P2
Type Package
Main Project JJM-Augmentation of ARWSS to Nooranad, Chunakkara, Palamel and Thamarakulam Panchayaths -Renovation to 10 mld WTP Pattoor, Supplying and Laying of Distribution lines and giving House connections in Nooranadu, Chunakkara, Palamel Thamarakkulam Panchayaths and providing FHTC
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM-SUPPLYING AND LAYING OF 13KM PIPE LINE NETWORK-JJM-SUPPLY AND LAYING OF 13KM PIPE LINE NETWORK FOR NOORANAD,PALAMEL,CHUNAKKARA AND THAMARAKULAM GRAMAPANCHAYATH-Pipeline Work-1-Additional supply of 90mm and 110mm, 8kg/cm2 PVC pipe lines for new house connections
Status On-going
District Alappuzha
Executing Office Alappuzha Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 27412551
TS Number WRD/KWA-CE(CR)/EST_TS/3170/2023_26_1_1
Technical specification
Contractor Dinesh N.R (Mob: 9847856881)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package Date is not specified
Scheduled date of Completion as per agreement Date is not specified
Expected date of Completion Date is not specified

Processing Dates

TS Date 20 Jul 2023
Estimate Approval 20 Jul 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Alappuzha Project Dn PM
Date: 29/06/2024

Work in progress | 96% Completed

Work completed Final bill under processing .

Alappuzha Project Dn PM
Date: 28/06/2024

Work in progress | 96% Completed

Work completed Final bill under processing.