Jal Jeevan Mission (JJM)-RWSS to Karukutty & Mookkannoor -Multi Village Scheme - Extension of Pipe Line and Providing Functional House Hold Tap Connections (FHTC) to Rural House Holds in various Wards of Karukutty Panchayath and Allied Works.-Part 1

Project Jal Jeevan Mission (JJM)-RWSS to Karukutty & Mookkannoor -Multi Village Scheme - Extension of Pipe Line and Providing Functional House Hold Tap Connections (FHTC) to Rural House Holds in various Wards of Karukutty Panchayath and Allied Works.-Part 1
Project Code EKMJJM08203266P4
Type Package
Main Project Jal Jeevan Mission- Multi Village Scheme - RWSS to Karukutty and Mookkannoor Panchayaths - Replacement of 315 mm PVC pipe to 300 mm DI K9 pipe, Extension of pipe line, Providing FHTC and allied works in Karukutty Panchayath
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission (JJM)-RWSS to Karukutty & Mookkannoor -Multi Village Scheme - Extension of Pipe Line and Providing Functional House Hold Tap Connections (FHTC) to Rural House Holds in various Wards of Karukutty Panchayath and Allied Works.-Part 1
Status On-going
District Ernakulam
Executing Office Aluva JJM Section
Agreement Number
Agreement Date
TS Amount (Rs) 48000000
TS Number WRD/KWA-CE(CR)/EST_TS/14925/2022_26_1_1 Dated: 16-05-2023
Technical specification
Contractor A M UBADULLA (Mob: 9447166558)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 30/07/2023
Scheduled date of Completion as per agreement 29 Oct 2023
Expected date of Completion 31/03/2024

Processing Dates

TS Date 16 May 2023
Estimate Approval 16 May 2023
NIT Approval 29 May 2023
Tender Closing 09 Jun 2023
Technichal Pre-Qualification 15 Jun 2023
Price bid opening 12 Jun 2023

Approval Dates

Workorder Date 08 Jul 2023
NA 20 Jul 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Aluva AE JJM
Date: 10/06/2024

Work in progress | 66% Completed

328 connections given out of 2021 connections. balance connection work ongoing. Pipeline work completed. .

Aluva AE JJM
Date: 07/06/2024

Work in progress | 66% Completed

328 connections given out of 2021 connections. balance connection work ongoing. Pipeline work completed. .