- Home
- Urban Agglomeration 2022-23 karakulam pa...
Urban Agglomeration 2022-23 karakulam panchayath
Project |
Urban Agglomeration 2022-23 karakulam panchayath |
Project Code |
TVMGOK062215891 |
Type |
Main project |
Funding Agency |
GOK |
Category |
Urban Water Supply Scheme – Others |
Type of scheme |
Water Supply |
Scheme |
2215-02-106-97 |
Description |
Urban Agglomeration 2022-23 karakulam panchayath |
Status |
On-going |
District |
Thiruvananthapuram |
Executing Office |
Aruvikkara HW Dn |
AS Amount (Rs) |
88996000
|
AS Number |
GO(Rt)No.4221/2022/Fin |
TS Amount (Rs) |
|
TS Number |
|
Total Bill Submitted (Rs) |
|
Total Bill Paid (Rs) |
|
Population Benefitted |
|
Capacity in MLD |
|
Actual Project Completion Date |
Date is not specified |
Coverage |
|
Packages
No. |
Project Name |
Location |
View |
1 |
Others-Urban Agglomeration-UA 20-21 Karakulam Panchayath Providing Transmission Line-DI pipe-Kepco to Kallayam -part 3/4 -pipeline work-pipeline work. |
Nedumangad WW Sn |
|
2 |
Others- Urban Agglomeration -UA 20-21 Providing water supply facilities OHSR 1LL in Karakulam Panchayath-Myladupara part 2/4 pipeline work |
Nedumangad WW Sn |
|
3 |
Others-Urban Agglomeration-Urban Agglomeration-UA 20-21 Karakulam Panchayath Providing 2LL OHSR at Kallayam and allied works 1/4-Pipeline work |
Nedumangad WW Sn |
|
No status have been added to this project
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
Date is not specified |
Scheduled date of Completion of the Project |
Date is not specified |
Expected date of Completion |
Date is not specified |