Jal Jeevan Mission phase II Providing Functional Household tap connections and laying distribution lines for last mile connectivity at Thrikkovilvattom Panchayath

Project Jal Jeevan Mission phase II Providing Functional Household tap connections and laying distribution lines for last mile connectivity at Thrikkovilvattom Panchayath
Project Code KLMJJM042313896P1
Type Package
Main Project Jal Jeevan Mission phase II Providing Functional Household tap connections and laying distribution lines for last mile connectivity at Thrikkovilvattom Panchayath
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission phase II Providing Functional Household tap connections and laying distribution lines for last mile connectivity at Thrikkovilvattom Panchayath
Status On-going
District Kollam
Executing Office Kollam Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 71450000
TS Number 6790/2022-23
Technical specification
Contractor RAJEEV. K (Mob: 9447503361)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 23/02/2023
Scheduled date of Completion as per agreement 22 Feb 2024
Expected date of Completion 22/02/2024

Processing Dates

TS Date 26 Nov 2022
Estimate Approval 26 Nov 2022
NIT Approval 01 Dec 2022
Tender Closing 24 Feb 2022
Technichal Pre-Qualification 24 Jan 2023
Price bid opening 25 Jan 2023

Approval Dates

Workorder Date 04 Feb 2022
NA 23 Feb 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kollam Project Dn AE
Date: 29/06/2024

Work in progress | 46% Completed

745 nos FHTC installation and 11898.05m pipe laying completed, Concrete road restoration work 738.009m3 completed .

Kollam Project Dn AE
Date: 28/06/2024

Work in progress | 46% Completed

745 nos FHTC installation and 11898.05m pipe laying completed, Concrete road restoration work 738.009m3 completed .