Drilling of New Tube well at Driver Junction (Ward 21) in Thodiyoor Panchayath

Project Drilling of New Tube well at Driver Junction (Ward 21) in Thodiyoor Panchayath
Project Code KLMDEPO102518092P1
Type Package
Main Project DEPOSIT-Oachira Block Panchayath - RWSS to Thodiyoor-Drilling of New Tube well at Driver Junction (Ward 21) in Thodiyoor Panchayath
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description DEPOSIT-Oachira Block Panchayath - RWSS to Thodiyoor-Drilling of New Tube well at Driver Junction (Ward 21) in Thodiyoor Panchayath
Status On-going
District Kollam
Executing Office Chavara PH Sn
Agreement Number
Agreement Date
TS Amount (Rs) 2296640
TS Number 16945/2025-2026
Technical specification DEPOSIT-Oachira Block Panchayath - RWSS to Thodiyoor-Drilling of New Tube well at Driver Junction (Ward 21) in Thodiyoor Panchayath

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 10/08/2026
Scheduled date of Completion as per agreement 09 Jul 2026
Expected date of Completion 10/09/2026

Processing Dates

Estimate Approval 04 Oct 2025
TS Date 16 Oct 2025

Approval Dates

NA 31 Dec 2025
Workorder Date 25 Oct 2025

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Chavara AE
Date: 07/09/2026

Work has been completed | 100% Completed

Work completed.

Chavara AE
Date: 01/09/2026

Work in progress | 90% Completed

Pump erection ongoing.