State plan -Construction of 27 LL OHSR,CW pump supply & erection, distribution network for Cherpulassery muncipality phase-l

Project State plan -Construction of 27 LL OHSR,CW pump supply & erection, distribution network for Cherpulassery muncipality phase-l
Project Code PKDGOK072113918
Type Main project
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Scheme 4215-01-800-89
Description The proposed project is for providing Comprehensive Water Supply Scheme to the entire population of Cherpulassery Municipality at the rate 150 lpcd for the projected population of 45413 forthe year 2050 . The scheme CWSS to Cherpulassery and Adj. Panchayaths is a comprehensive water supply scheme to Cherpulassery Municipality, Anangandi, Thrikkediri and Chalavara Panchayaths. The project is proposed to be executed in 3 phases. Phase – I shall comprise of the common components along with the OHSRs, GLSRs, Clear Water pumps, Clear Water Pumping / Gravity mains, distribution network of the three panchayaths. Phase – II & III shall comprise of the components required for providing water supply to Cherpulassery Municipality and providing FHTCs.
Status On-going
District Palakkad
Executing Office Palakkad Project Dn
AS Amount (Rs) 100000000
AS Number G.O.(Rt)No.350/2021/WRD
TS Amount (Rs) 100000000
TS Number TS/2022-23/2022/26147
Total Bill Submitted (Rs) 70266430
Total Bill Paid (Rs) 70266430
Population Benefitted 45413
Capacity in MLD 22.00
Actual Project Completion Date 31 Dec 2024
Coverage Cherppulassery muncipality & adjoining panchayath
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 State plan -Construction of 27LL OHSR,CW pump supply & erection, distribution network for Cherpulassery muncipality phase-l Project Division Palakkad

Overall Project Status

Status Date Overall Project Status Project Officer Contact
25 Mar 2025 27LL OHSR Structure Completed, Painting completed, Handrail works completed. 40 HP - 2 nos CW pump sets supplied and erected, pipe connection work in progress . Laying - 350 mm DI 500 m/500m completed, 400 mm DI 1160 /1160 m completed, 450 mm DI 450/450m completed. 600 mm DI 460/460 m completed, 160 mm PE 3525/3525m completed.Electricity connection to be obtained in JJM Cherpulaseery Head works. Palakkad Proj Dn AE 4
19 Feb 2025 27LL OHSR Structure Completed, Painting completed, Handrail works completed. 40 HP - 2 nos CW pump sets supplied and erected . Laying - 350 mm DI 500 m/500m completed, 400 mm DI 1160 /1160 m completed, 450 mm DI 450/450m completed. 600 mm DI 460/460 m completed, 160 mm PE 3525/3525m completed. Palakkad Proj Dn AE 4
11 Feb 2025 27LL OHSR Structure Completed, Painting in progressing. Handrail works completed. 40 HP - 2 nos CW pump sets supplied and erected.350 mm DI 500 m/500m completed, 400 mm DI 1160 /1160 m completed, 450 mm DI 450/450m completed. 600 mm DI 460/460 m completed, 160 mm PE 3525/3525m completed. Palakkad Proj Dn AE 4
17 Dec 2024 27LL OHSR Structure Completed, Painting in progressing.Handrail works completed. 40 HP - 2 nos CW pump sets supplied by contractor.350 mm DI 500 m/500m completed, 400 mm DI 1160 /1160 m completed, 450 mm DI 450/450m completed. 600 mm DI 460/460 m completed, 160 mm PE 3525/3525m completed. Palakkad Proj Dn AE 4
03 Dec 2024 27LL OHSR Structure Completed, Painting in progressing.Handrail works completed. 40 HP - 2 nos CW pump sets supplied by contractor.350 mm DI 500 m/500m completed, 400 mm DI 1160 /1160 m completed, 450 mm DI 450/450m completed. 600 mm DI 460/460 m completed, 160 mm PE 3525/3525m completed. Palakkad Proj Dn AE 4

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 13/10/2022
Scheduled date of Completion of the Project 12 Apr 2023
Expected date of Completion 31/05/2025

Processing Dates

AS Date 08 Jul 2021
TS Date 30 Jun 2022

Other details

Project Officers View