- Home
- TSS Design Construction Commissioning &...
TSS Design Construction Commissioning & Maintenance of pumping station and allied works at Akkulam-well cum pump house manhole laying pipe for interconnection work etc
Project |
TSS Design Construction Commissioning & Maintenance of pumping station and allied works at Akkulam-well cum pump house manhole laying pipe for interconnection work etc |
Project Code |
TVMAMRUT1117696 |
Type |
Main project |
Funding Agency |
AMRUT |
Category |
AMRUT |
Type of scheme |
Water Supply |
Scheme |
AMRUT |
Description |
The work consist of
1) 2 nos of well of dia 6.5 m
2) Grid chamber of size 12.7x4.9
3)Construction of pump house compound wall
4)construction of 4 nos of MH |
Status |
On-going |
District |
Thiruvananthapuram |
Executing Office |
Trivandrum Project Dn |
AS Amount (Rs) |
40000000
|
AS Number |
GO(RT)No 3530/2017 |
TS Amount (Rs) |
36100000 |
TS Number |
TS/2017-2018/2018/580 |
Total Bill Submitted (Rs) |
25898822 |
Total Bill Paid (Rs) |
25898822 |
Population Benefitted |
46000 |
Capacity in MLD |
107.00 |
Actual Project Completion Date |
10 Jan 2020 |
Coverage |
Kuzhivila Akkulam |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
TSS Design Construction Commissioning & Maintenance of pumping station and allied works at Akkulam-well cum pump house manhole laying pipe for interconnection work etc |
Trivandrum Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
16 May 2024 |
All RCC work for well 1,2 , Grid chamber became completed . The substation building structural work ,plastering works completed , The construction of the retaining wall and beams are going on. |
Thiruvananthapuram Project AE6 |
|
22 Apr 2024 |
All RCC work for well 1,2 , Grid chamber became completed . The substation building structural work ,plastering works completed , The construction of the retaining wall and beams are going on. |
Thiruvananthapuram Project AE6 |
|
09 Apr 2024 |
All RCC work for well 1,2 , Grid chamber became completed . The substation building structural work ,plastering works completed , The construction of the retaining wall for compound wall is going on. |
Thiruvananthapuram Project AE6 |
|
01 Apr 2024 |
All RCC work for well 1,2 , Grid chamber became completed . The substation building structural work ,plastering works completed , The construction of the retaining wall for compound wall is going on. |
Thiruvananthapuram Project AE6 |
|
27 Mar 2024 |
All RCC work for well 1,2 , Grid chamber became completed . The substation building structural work ,plastering works completed , The construction of the retaining wall for compound wall is going on. |
Thiruvananthapuram Project AE6 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
11/01/2019 |
Scheduled date of Completion of the Project |
10 Jan 2020 |
Expected date of Completion |
31/03/2024 |
Processing Dates
AS Date |
02 Nov 2017 |
TS Date |
27 Feb 2018 |