Status Date |
Overall Project Status |
Project Officer |
Contact |
16 May 2024 |
Work in progress | 89% Completed | 16/05/2024
Road restoration work progress at various places. HDD WORK at stopped on , Ms pipe carriying bridge work completed at thrippalur . erimayur by passwork in progress (131M /220M), venganur pipe carriying brige work in progress, PWD Permanent road restoration work in progress at various places, Total pipes supplied- -800 KM, laid total 733.392 km,/out of 880km FHTC-21275/out of 27786, ,erimayur HDD work completed and pipe carrying bridge work completed 1). Kavassery panchayath laid length – 155.046km 2).Erimayoor panchayath – 166.319km 3).Pallassena panchayath – 110.413 km 4).Elavenchery panchayath – 89.153km 5).Alathur panchayath- 124.431km 6) Puthukkode panchayath- 88.030 km TOTAL laid length – 725.00km 7.) 10LL OHSR - 10 LL OHSR – Painting work completed and compound wall plastering work in progress 8). 33 LL OHSR – plastering work in progress and column pipe erect ing work progress 9) 40LL OHSR- plastering work in progress and column pipe erecting work progress FHTC- Alathur – 5491/out of 6688, Erimayur – 4136/ out of 3043 Kavassery – 5425/out of 7519 Pudukkode – 1340/out of 2461 Pallassena – 2848/out of 6058 Elevanchery - 2035/out of 2017 total -21275.00No ( FHTC-4th bill-1319 5TH BILL-1301 billed), 6th bill-1669,7 th bill-1509 ,8th bill-2375 Nos,9th bill- 1685Nos,10th bill-1887 ,11 th bill-3710 Nos ,12th bill-3546 nos, 13 th bill-1340,14 th bill—1551 ,15th bill -462 total- 21853 No provided |
Chittur Project Dn - AE 1 |
|
02 May 2024 |
Work in progress | 88% Completed | 02/05/2024
HDD WORK at swathi junction, erimayur by passwork in progress (131M /220M), venganur pipe carriying brige work in progress, PWD Permanent road restoration work in progress at various places, Total pipes supplied- -800 KM, laid total 725.62km,/out of 880km FHTC-21275/out of 27786, ,erimayur HDD work completed and pipe carrying bridge work completed 1). Kavassery panchayath laid length – 155.046km 2).Erimayoor panchayath – 158.551km 3).Pallassena panchayath – 110.413 km 4).Elavenchery panchayath – 89.153km 5).Alathur panchayath- 124.431km 6) Puthukkode panchayath- 88.030 km TOTAL laid length – 725.00km 7.) 10LL OHSR - 10 LL OHSR – Painting work completed and compound wall plastering work in progress 8). 33 LL OHSR – plastering work in progress and column pipe erect ing work progress 9) 40LL OHSR- plastering work in progress and column pipe erecting work progress FHTC- Alathur – 5491/out of 6688, Erimayur – 4136/ out of 3043 Kavassery – 5425/out of 7519 Pudukkode – 1340/out of 2461 Pallassena – 2848/out of 6058 Elevanchery - 2035/out of 2017 total -21275.00No ( FHTC-4th bill-1319 5TH BILL-1301 billed), 6th bill-1669,7 th bill-1509 ,8th bill-2375 Nos,9th bill- 1685Nos,10th bill-1887 ,11 th bill-3710 Nos ,12th bill-3546 nos, 13 th bill-1340,14 th bill—1551 ,15th bill -462 total- 21853 No provided |
Chittur Project Dn - AE 1 |
|
23 Apr 2024 |
Work in progress | 88% Completed | 23/04/2024
HDD WORK at swathi junction, erimayur by passwork in progress (131M /220M), venganur pipe carriying brige work in progress, PWD Permanent road restoration work in progress at various places, Total pipes supplied- -800 KM, laid total 725.62km,/out of 880km FHTC-21275/out of 27786, ,erimayur HDD work completed and pipe carrying bridge work completed 1). Kavassery panchayath laid length – 155.046km 2).Erimayoor panchayath – 158.551km 3).Pallassena panchayath – 110.413 km 4).Elavenchery panchayath – 89.153km 5).Alathur panchayath- 124.431km 6) Puthukkode panchayath- 88.030 km TOTAL laid length – 725.00km 7.) 10LL OHSR - 10 LL OHSR – Painting work completed and compound wall plastering work in progress 8). 33 LL OHSR – plastering work in progress and column pipe erect ing work progress 9) 40LL OHSR- plastering work in progress and column pipe erecting work progress FHTC- Alathur – 5491/out of 6688, Erimayur – 4136/ out of 3043 Kavassery – 5425/out of 7519 Pudukkode – 1340/out of 2461 Pallassena – 2848/out of 6058 Elevanchery - 2035/out of 2017 total -21275.00No ( FHTC-4th bill-1319 5TH BILL-1301 billed), 6th bill-1669,7 th bill-1509 ,8th bill-2375 Nos,9th bill- 1685Nos,10th bill-1887 ,11 th bill-3710 Nos ,12th bill-3546 nos, 13 th bill-1340,14 th bill—1551 ,15th bill -462 total- 21853 No provided |
Chittur Project Dn - AE 1 |
|
11 Apr 2024 |
Work in progress | 88% Completed | 11/04/2024
HDD WORK at swathi junction, erimayur by passwork in progress (131M /220M), venganur pipe carriying brige work in progress, PWD Permanent road restoration work in progress at various places, Total pipes supplied- -800 KM, laid total 725.62km,/out of 880km FHTC-21275/out of 27786, ,erimayur HDD work completed and pipe carrying bridge work completed 1). Kavassery panchayath laid length – 155.046km 2).Erimayoor panchayath – 158.551km 3).Pallassena panchayath – 110.413 km 4).Elavenchery panchayath – 89.153km 5).Alathur panchayath- 124.431km 6) Puthukkode panchayath- 88.030 km TOTAL laid length – 725.00km 7.) 10LL OHSR - 10 LL OHSR – Painting work completed and compound wall plastering work in progress 8). 33 LL OHSR – plastering work in progress and column pipe erect ing work progress 9) 40LL OHSR- plastering work in progress and column pipe erecting work progress FHTC- Alathur – 5491/out of 6688, Erimayur – 4136/ out of 3043 Kavassery – 5425/out of 7519 Pudukkode – 1340/out of 2461 Pallassena – 2848/out of 6058 Elevanchery - 2035/out of 2017 total -21275.00No ( FHTC-4th bill-1319 5TH BILL-1301 billed), 6th bill-1669,7 th bill-1509 ,8th bill-2375 Nos,9th bill- 1685Nos,10th bill-1887 ,11 th bill-3710 Nos ,12th bill-3546 nos, 13 th bill-1340,14 th bill—1551 ,15th bill -462 total- 21853 No provided |
Chittur Project Dn - AE 1 |
|
05 Apr 2024 |
Work in progress | 88% Completed | 05/04/2024
HDD WORK at swathi junction, erimayur by passwork in progress (131M /220M), venganur pipe carriying brige work in progress, PWD Permanent road restoration work in progress at various places, Total pipes supplied- -800 KM, laid total 725.62km,/out of 880km FHTC-21275/out of 27786, ,erimayur HDD work completed and pipe carrying bridge work completed 1). Kavassery panchayath laid length – 155.046km 2).Erimayoor panchayath – 158.551km 3).Pallassena panchayath – 110.413 km 4).Elavenchery panchayath – 89.153km 5).Alathur panchayath- 124.431km 6) Puthukkode panchayath- 88.030 km TOTAL laid length – 725.00km 7.) 10LL OHSR - 10 LL OHSR – Painting work completed and compound wall plastering work in progress 8). 33 LL OHSR – plastering work in progress and column pipe erect ing work progress 9) 40LL OHSR- plastering work in progress and column pipe erecting work progress FHTC- Alathur – 5491/out of 6688, Erimayur – 4136/ out of 3043 Kavassery – 5425/out of 7519 Pudukkode – 1340/out of 2461 Pallassena – 2848/out of 6058 Elevanchery - 2035/out of 2017 total -21275.00No ( FHTC-4th bill-1319 5TH BILL-1301 billed), 6th bill-1669,7 th bill-1509 ,8th bill-2375 Nos,9th bill- 1685Nos,10th bill-1887 ,11 th bill-3710 Nos ,12th bill-3546 nos, 13 th bill-1340,14 th bill—1551 ,15th bill -462 total- 21853 No provided |
Chittur Project Dn - AE 1 |
|