| Project | JJM Ummannoor Pt-Restoration work-Restoration of Grama Panchayath roads at various places in Ummannoor |
|---|---|
| Project Code | KLMJJM08203133P4 |
| Type | Package |
| Main Project | Jal Jeevan Mission- Providing FHTC at Ummannoor Grama panchayath in Kollam I District |
| Funding Agency | JJM |
| Category | JJM |
| Type of scheme | Water Supply |
| Scheme | 4215-01-102-92-01 |
| Description | Total length of panchayt road restoration for 13000 m is included in the estimate. Estimate include restoration by concreting and filling pot holes in tar road and restoration of crossing in tar surface by chipping carpet |
| Status | On-going |
| District | Kollam |
| Executing Office | Valakom PH Sn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 12997000 |
| TS Number | WRD/KWA-CE(SR)/EST_TS/3181/2024_5_1_1 |
| Technical specification | Total length of panchayt road restoration for 13000 m is included in the estimate. Estimate include restoration by concreting and filling pot holes in tar road and restoration of crossing in tar surface by chipping carpet |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | Date is not specified |
|---|---|
| Scheduled date of Completion as per agreement | 02 Jan 2025 |
| Expected date of Completion | 30/06/2025 |
| TS Date | 13 Jul 2024 |
|---|---|
| Estimate Approval | 06 Apr 2024 |
| NIT Approval | 19 Jul 2024 |
| Tender Closing | 30 Jul 2024 |
| Price bid opening | 30 Jul 2024 |
| NA | 03 Oct 2024 |
|---|
| Valakom PH Sn AE |
| Date: 29/07/2025 |
Work has been completed | 100% Completed
work completed on 30/06/2025.
| Valakom PH Sn AE |
| Date: 18/06/2025 |
Work in progress | 75% Completed
7.5 km road concrete work completed ,work progressing in ward 2.