AMRUT - 2017-18 WSS to Guruvayur Municipality in Thrissur District-Laying distribution networks in Thaikkad zone - Guruvayur Municipality( Revised AS -12.13Cr)
Project |
AMRUT - 2017-18 WSS to Guruvayur Municipality in Thrissur District-Laying distribution networks in Thaikkad zone - Guruvayur Municipality( Revised AS -12.13Cr) |
Project Code |
TCRGOI0218550 |
Type |
Main project |
Funding Agency |
AMRUT |
Category |
AMRUT |
Type of scheme |
Water Supply |
Scheme |
AMRUT |
Description |
Components:
1) Distribution network-450mm to 160mmPVC-20140m
|
Status |
On-going |
District |
Thrissur |
Executing Office |
Nattika Project Dn |
AS Amount (Rs) |
121300000
|
AS Number |
GO(Rt) No. 3170/2017/LSGD |
TS Amount (Rs) |
100000000 |
TS Number |
TS/2018-2019/2018/2554 |
Total Bill Submitted (Rs) |
86025834 |
Total Bill Paid (Rs) |
86025834 |
Population Benefitted |
17854 |
Capacity in MLD |
3.76 |
Actual Project Completion Date |
11 Nov 2022 |
Coverage |
Wards of Thaikkad zone in Guruvayoor Muncipality
Population benefitted - 17854 |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
AMRUT-2017-18 WSS to Guruvayur Municipality in thrissur District-Distribution net work for thyikkad zone- supply,laying,testing and commissioning 200 mm to 450 mm DI K9 and 160 mm PVC for distribution net work for thikkad zone- Additional works-railway line crossing at paluvai by push through method |
Nattika Project Dn |
|
2 |
AMRUT - 2017-18 WSS to Guruvayur Municipality in Thrissur District-Laying distribution networks in Thaikkad zone |
Nattika Project Dn |
|
3 |
AMRUT - WSS to Guruvayur Muncipality - Distribution Network to Thaikkad zone - Balance work- Triprayar Kanjany Chavakkad road |
Nattika Project Dn |
|
4 |
AMRUT-WSS to Guruvayur Muncipality in Thrissur District-Clear water pumping main balance work(new route)- coveying and Laying 600 mm & 450 mm DI pipe from proposed OHSR at Edappily Jaram road for interconnecting with existing distribution Main near pancharamukku( Thaikkad zone distribution ) |
Nattika Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
22 Feb 2024 |
Work completed except one culvert crossing and railway crossing work. |
Nattika Project Dn |
|
20 Oct 2023 |
Work completed except one culvert crossing and railway crossing work. |
Nattika Project Dn |
|
10 Oct 2023 |
Work completed except one culvert crossing and railway crossing work. |
Nattika Project Dn |
|
27 Sep 2023 |
Work completed except one culvert crossing and railway crossing work. |
Nattika Project Dn |
|
21 Sep 2023 |
Work completed except one culvert crossing and railway crossing work. |
Nattika Project Dn |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
31/10/2018 |
Scheduled date of Completion of the Project |
18 Sep 2019 |
Expected date of Completion |
31/07/2023 |
Processing Dates
AS Date |
22 Feb 2018 |
TS Date |
09 Apr 2018 |