AMRUT - 2017-18 WSS to Guruvayur Municipality in Thrissur District-Laying distribution networks in Thaikkad zone - Guruvayur Municipality( Revised AS -12.13Cr)

Project AMRUT - 2017-18 WSS to Guruvayur Municipality in Thrissur District-Laying distribution networks in Thaikkad zone - Guruvayur Municipality( Revised AS -12.13Cr)
Project Code TCRGOI0218550
Type Main project
Funding Agency AMRUT
Category AMRUT
Type of scheme Water Supply
Scheme AMRUT
Description Components: 1) Distribution network-450mm to 160mmPVC-20140m
Status On-going
District Thrissur
Executing Office Nattika Project Dn
AS Amount (Rs) 121300000
AS Number GO(Rt) No. 3170/2017/LSGD
TS Amount (Rs) 100000000
TS Number TS/2018-2019/2018/2554
Total Bill Submitted (Rs) 86025834
Total Bill Paid (Rs) 86025834
Population Benefitted 17854
Capacity in MLD 3.76
Actual Project Completion Date 11 Nov 2022
Coverage Wards of Thaikkad zone in Guruvayoor Muncipality Population benefitted - 17854
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 AMRUT-2017-18 WSS to Guruvayur Municipality in thrissur District-Distribution net work for thyikkad zone- supply,laying,testing and commissioning 200 mm to 450 mm DI K9 and 160 mm PVC for distribution net work for thikkad zone- Additional works-railway line crossing at paluvai by push through method Nattika Project Dn
2 AMRUT - 2017-18 WSS to Guruvayur Municipality in Thrissur District-Laying distribution networks in Thaikkad zone Nattika Project Dn
3 AMRUT - WSS to Guruvayur Muncipality - Distribution Network to Thaikkad zone - Balance work- Triprayar Kanjany Chavakkad road Nattika Project Dn
4 AMRUT-WSS to Guruvayur Muncipality in Thrissur District-Clear water pumping main balance work(new route)- coveying and Laying 600 mm & 450 mm DI pipe from proposed OHSR at Edappily Jaram road for interconnecting with existing distribution Main near pancharamukku( Thaikkad zone distribution ) Nattika Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
22 Feb 2024 Work completed except one culvert crossing and railway crossing work. Nattika Project Dn
20 Oct 2023 Work completed except one culvert crossing and railway crossing work. Nattika Project Dn
10 Oct 2023 Work completed except one culvert crossing and railway crossing work. Nattika Project Dn
27 Sep 2023 Work completed except one culvert crossing and railway crossing work. Nattika Project Dn
21 Sep 2023 Work completed except one culvert crossing and railway crossing work. Nattika Project Dn

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 31/10/2018
Scheduled date of Completion of the Project 18 Sep 2019
Expected date of Completion 31/07/2023

Processing Dates

AS Date 22 Feb 2018
TS Date 09 Apr 2018

Other details

Project Officers View