| Project | MLA-SDF-2020-21-Sri.M.Mukesh MLA-KollamLAC-Extension of pipe line to Vellikkadu in Neeravil Division in kollam Corporation- |
|---|---|
| Project Code | KLMDC-LAC/ADS/SDF/KSCADC07219764P1 |
| Type | Package |
| Main Project | MLA-SDF-2020-21-Sri.M.Mukesh MLA-KollamLAC-Extension of pipe line to Vellikkadu in Neeravil Division in Kollam Corporation |
| Funding Agency | DC-LAC/ADS/SDF/KSCADC |
| Category | MLA SDF |
| Type of scheme | Water Supply |
| Scheme | DC-LAC/ADS/SDF/KSCADC |
| Description | MLA-SDF-2020-21-Sri.M.Mukesh MLA-KollamLAC-Extension of pipe line to Vellikkadu in Neeravil Division in kollam Corporation- |
| Status | On-going |
| District | Kollam |
| Executing Office | Kollam WS Sn 2 |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 460000 |
| TS Number | TS/2021-2022/2020/21740 |
| Technical specification | Extension of pipe line to Vellikkadu in Neeravil Division in kollam Corporation- |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 28/02/2022 |
|---|---|
| Scheduled date of Completion as per agreement | 30 Mar 2022 |
| Expected date of Completion | 30/06/2022 |
| TS Date | 03 Jan 2022 |
|---|---|
| Estimate Approval | 03 Jan 2022 |
| NIT Approval | 04 Jan 2022 |
| Tender Closing | 14 Jan 2022 |
| Technichal Pre-Qualification | 14 Jan 2022 |
| Price bid opening | 14 Jan 2022 |
| Workorder Date | 08 Feb 2022 |
|---|---|
| NA | 28 Feb 2022 |
| Kollam WS Sn 2 - AE |
| Date: 11/07/2022 |
Work has been completed | 100% Completed
Bill submitted.
| Kollam WS Sn 2 - AE |
| Date: 30/06/2022 |
Work has been completed | 100% Completed
Work completed..