Project | KIIFB-TRAN11- WRD025-10- Drinking Water Project in Coastal panchayaths of Chirayinkeezhu Constituency - phase I & II |
---|---|
Project Code | TVMKIIFB0219541P1 |
Type | Package |
Main Project | KIIFB-TRAN11- WRD025-10- Drinking Water Project in Coastal panchayaths of Chirayinkeezhu Constituency - phase I & II |
Funding Agency | KIIFB |
Category | KIIFB WATER SUPPLY SCHEME |
Type of scheme | Water Supply |
Scheme | KIIFB |
Description | The project is proposed to meet the demand of potable water supply to the entire population in Chirayinkeezhu, Kadakkavoor , Anchuthengu Panchayat and Adjoining Panchayats in Chirayinkeezhu constituency. |
Status | Completed |
District | Thiruvananthapuram |
Executing Office | Trivandrum Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 177860000 |
TS Number | TS/2019-2020/2019/11329 Dated: 09-08-2019 |
Technical specification | 15 MLD plant,9m dia well cum pump house,pumping main etc |
Contractor | M/s Chicago Construction International (P) Ltd (Mob: 9447111906) |
Issue date | Solved On | Action Taken On | Category | Description | Comments | Issue Status |
---|---|---|---|---|---|---|
30 May 2022 | Pending | Pending | Approval/Permissions Related (from other departments excluding road cut permission and land related) | HT Connection from KSEB not received though an amount of Rs.5,90,333.00 was paid by KWA on their demand on 24.05.2022. | No comments available. | Pending |
15 Feb 2022 | Pending | Pending | Approval/Permissions Related (from other departments excluding road cut permission and land related) | KSEB HT Connection request for WTP and Raw Water Pump House on hold for want of completion of pending dues of existing LT connection in same premise. | No comments available. | Pending |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 03/06/2020 |
---|---|
Scheduled date of Completion as per agreement | 09 Sep 2021 |
Expected date of Completion | 31/07/2022 |
TS Date | 09 Aug 2019 |
---|---|
Estimate Approval | 09 Aug 2019 |
NIT Approval | 29 Oct 2019 |
Tender Closing | 31 Oct 2019 |
Technichal Pre-Qualification | 16 Nov 2019 |
Price bid opening | 07 Jan 2020 |
Workorder Date | 10 Mar 2020 |
---|---|
NA | 18 Mar 2020 |
Thiruvananthapuram Project AE5 |
Date: 03/04/2023 |
Work has been completed | 100% Completed
The work was completed on 30.09.2022 and commissioned by 10.11.2022. The total AS sanctioned by KIIFB for the work was Rs.19,86,76,128.00. TS later sanctioned by KWA & KIIFB for Part 1 work which include WTP,RWPM, CWPM, RWPH, CWPH, Well and part 2 which include power line extension and Land acquisition etc. was 17,78,52,271.00. Land acquisition expense was not inquired as the development was made on KWA own land and revenue land. All the work included in the scope of Part1 and Part 2 work have been completed on 30.09.2022 and commissioned on 10.11.2022. .
Thiruvananthapuram Project AE5 |
Date: 23/12/2022 |
Work has been completed | 100% Completed
The work completed. Tested and Commissioned on 10.11.2022. Physical completion of all work on 30.09.2022..