KIIFB-TRAN11- WRD025-10- Drinking Water Project in Coastal panchayaths of Chirayinkeezhu Constituency - phase I & II

Project KIIFB-TRAN11- WRD025-10- Drinking Water Project in Coastal panchayaths of Chirayinkeezhu Constituency - phase I & II
Project Code TVMKIIFB0219541P1
Type Package
Main Project KIIFB-TRAN11- WRD025-10- Drinking Water Project in Coastal panchayaths of Chirayinkeezhu Constituency - phase I & II
Funding Agency KIIFB
Category KIIFB WATER SUPPLY SCHEME
Type of scheme Water Supply
Scheme KIIFB
Description The project is proposed to meet the demand of potable water supply to the entire population in Chirayinkeezhu, Kadakkavoor , Anchuthengu Panchayat and Adjoining Panchayats in Chirayinkeezhu constituency.
Status Completed
District Thiruvananthapuram
Executing Office Trivandrum Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 177860000
TS Number TS/2019-2020/2019/11329 Dated: 09-08-2019
Technical specification 15 MLD plant,9m dia well cum pump house,pumping main etc
Contractor M/s Chicago Construction International (P) Ltd (Mob: 9447111906)

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
30 May 2022 Pending Pending Approval/Permissions Related (from other departments excluding road cut permission and land related) HT Connection from KSEB not received though an amount of Rs.5,90,333.00 was paid by KWA on their demand on 24.05.2022. No comments available. Pending
15 Feb 2022 Pending Pending Approval/Permissions Related (from other departments excluding road cut permission and land related) KSEB HT Connection request for WTP and Raw Water Pump House on hold for want of completion of pending dues of existing LT connection in same premise. No comments available. Pending

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 03/06/2020
Scheduled date of Completion as per agreement 09 Sep 2021
Expected date of Completion 31/07/2022

Processing Dates

TS Date 09 Aug 2019
Estimate Approval 09 Aug 2019
NIT Approval 29 Oct 2019
Tender Closing 31 Oct 2019
Technichal Pre-Qualification 16 Nov 2019
Price bid opening 07 Jan 2020

Approval Dates

Workorder Date 10 Mar 2020
NA 18 Mar 2020

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Thiruvananthapuram Project AE5
Date: 03/04/2023

Work has been completed | 100% Completed

The work was completed on 30.09.2022 and commissioned by 10.11.2022. The total AS sanctioned by KIIFB for the work was Rs.19,86,76,128.00. TS later sanctioned by KWA & KIIFB for Part 1 work which include WTP,RWPM, CWPM, RWPH, CWPH, Well and part 2 which include power line extension and Land acquisition etc. was 17,78,52,271.00. Land acquisition expense was not inquired as the development was made on KWA own land and revenue land. All the work included in the scope of Part1 and Part 2 work have been completed on 30.09.2022 and commissioned on 10.11.2022. .

Thiruvananthapuram Project AE5
Date: 23/12/2022

Work has been completed | 100% Completed

The work completed. Tested and Commissioned on 10.11.2022. Physical completion of all work on 30.09.2022..