JJM - Kasaragod District - Chengala Panchayath- WSS to Chengala, Muliyar , Madhur and Mogral Puthur Panchayaths - Reach 7 (Zone 5&6)-Laying Distribution system and providing FHTCs- from the new OHSRs at Cherkala and Indiranagar Colony.

Project JJM - Kasaragod District - Chengala Panchayath- WSS to Chengala, Muliyar , Madhur and Mogral Puthur Panchayaths - Reach 7 (Zone 5&6)-Laying Distribution system and providing FHTCs- from the new OHSRs at Cherkala and Indiranagar Colony.
Project Code KGDJJM092110786
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Chengala Panchayath- WSS to Chengala, Muliyar , Madhur and Mogral Puthur Panchayaths - Reach 7 (Zone 5&6)-Laying Distribution system and providing FHTCs- from the new OHSRs at Cherkala and Indiranagar Colony.
Status On-going
District Kasaragod
Executing Office Kanhangad Project Division
AS Amount (Rs) 1272000000
AS Number G.O(Rt)No.489/2021/WRD
TS Amount (Rs) 296100000
TS Number TS/2021-2022/2021/41412
Total Bill Submitted (Rs) 118366363
Total Bill Paid (Rs)
Population Benefitted 56781
Capacity in MLD 0.18
Actual Project Completion Date 17 Dec 2022
Coverage coverage area of RWSS to cherkkala

Packages

No. Project Name Location View
1 JJM - Kasaragod District - Chengala Panchayath- WSS to Chengala, Muliyar , Madhur and Mogral Puthur Panchayaths - Reach 7 (Zone 5&6)-Laying Distribution system and providing FHTCs- from the new OHSRs at Cherkala and Indiranagar Colony. Project Division Kannur ( KGD)

Overall Project Status

Status Date Overall Project Status Project Officer Contact
17 May 2024 97.88 kms Pipe line work completed out of 98.99 kms ,2434 nos HTC given, 1184 FHTC given ,1049 nos of FHTC billed. Pipe to be laid along NHAI road which is under formation construction and awaiting for NHAI s direction to start the work .cc 10th & part bill submiited.Time extension granted upto for 31.03.2024.Time extension applied for 30.06.2024 Kanhangad Proj Dn AE - 1
15 May 2024 97.88 kms Pipe line work completed out of 98.99 kms ,2434 nos HTC given, 1154 FHTC given ,1049 nos of FHTC billed. Pipe to be laid along NHAI road which is under formation construction and awaiting for NHAI s direction to start the work .cc 10th & part bill submiited.Time extension granted upto for 31.03.2024.Time extension applied for 30.06.2024 Kanhangad Proj Dn AE - 1
09 May 2024 97.88 kms Pipe line work completed out of 98.99 kms ,2434 nos HTC given, 1154 FHTC given ,1049 nos of FHTC billed. Pipe to be laid along NHAI road which is under formation construction and awaiting for NHAI s direction to start the work .cc 10th & part bill submiited.Time extension granted upto for 31.03.2024.Time extension applied for 30.06.2024 Kanhangad Proj Dn AE - 1
03 May 2024 97.88 kms Pipe line work completed out of 98.99 kms ,2434 nos HTC given, 1084 FHTC given ,1049 nos of FHTC billed. Pipe to be laid along NHAI road which is under construction and awaiting for NHAI s direction to enter the site .up to date bills submitted. cc 10th & part bill submiited.Time extension granted upto for 31.03.2024.Time extension applied for 30.06.2024 Kanhangad Proj Dn AE - 1
23 Apr 2024 97.88 kms Pipe line work completed out of 98.99 kms ,2434 nos HTC given, 1084 FHTC given ,1049 nos of FHTC billed. Pipe to be laid along NHAI road which is under construction and awaiting for NHAI s direction to enter the site .up to date bills submitted. cc 10th & part bill submiited.Time extension granted upto for 31.03.2024.Time extension applied for 30.06.2024 Kanhangad Proj Dn AE - 1

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 29/03/2022
Scheduled date of Completion of the Project 17 Dec 2022
Expected date of Completion 31/03/2024

Processing Dates

AS Date 18 Sep 2021
TS Date 14 Dec 2021

Other details

Project Officers View