Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

DEPOSIT-CSME-2025 -Bulk meter Water Connection to Sreerosh Citadel Appartment at Onden Road kannur-Bulk meter Water Connection to Sreerosh Citadel Appartment-Pipeline Work

Project DEPOSIT-CSME-2025 -Bulk meter Water Connection to Sreerosh Citadel Appartment at Onden Road kannur-Bulk meter Water Connection to Sreerosh Citadel Appartment-Pipeline Work
Project Code KNRDEPO012618159
Type Main project
Funding Agency DEPO
Category CSME
Type of scheme Water Supply
Scheme DEPO
Description DEPOSIT-CSME-2025 -Bulk meter Water Connection to Sreerosh Citadel Appartment at Onden Road kannur-Bulk meter Water Connection to Sreerosh Citadel Appartment-Pipeline Work
Status On-going
District Kannur
Executing Office Kannur WS Sub Dn
AS Amount (Rs) 690000
AS Number letter received from Director ,sreerosh Developers Pvt Ltd, dtd 05.01.2026
TS Amount (Rs) 690000
TS Number 25400/2025-2026
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date Date is not specified
Coverage

Packages

No. Project Name Location View
1 DEPOSIT-CSME-2025 -Bulk meter Water Connection to Sreerosh Citadel Appartment at Onden Road kannur-Bulk meter Water Connection to Sreerosh Citadel Appartment-Pipeline Work Kannur WS Sn 2

Overall Project Status

Status Date Overall Project Status Project Officer Contact
25 Sep 2026 Road cutting demand note issued.COP Submitted to higher office. Kannur WS Sn AE 2
14 Aug 2026 Work order issued. Site handed over. Road cutting permission pending. Kannur WS Sn AE 2
17 Jul 2026 Work order issued. Site handed over. Kannur WS Sn AE 2
07 Jul 2026 Work order issued. Site handed over. Kannur WS Sn AE 2
18 Jun 2026 Work order issued. Site handed over. Kannur WS Sn AE 2

No project review have been added to this project

Duration & Sanction dates

Date of start of Project Date is not specified
Scheduled date of Completion of the Project Date is not specified
Expected date of Completion Date is not specified

Processing Dates

AS Date 06 Jan 2026
TS Date 13 Jan 2026

Other details

Project Officers View