| Project | DRW 2022 -Providing temporary bund on the down stream side of Mylamoodu pump house |
|---|---|
| Project Code | KLMGOK03229535P1 |
| Type | Package |
| Main Project | DRW 2022 -Providing temporary bund on the down stream side of Mylamoodu pump house |
| Funding Agency | GOK |
| Category | DRW |
| Type of scheme | Water Supply |
| Scheme | 4215-01-800-89 |
| Description | Providing temporary bund on the down stream side of Mylamoodu pump house |
| Status | On-going |
| District | Kollam |
| Executing Office | Madathara Sn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 294000 |
| TS Number | TS/2021-2022/2022/11531 |
| Technical specification | Providing temporary bund |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 01/04/2022 |
|---|---|
| Scheduled date of Completion as per agreement | 15 Apr 2022 |
| Expected date of Completion | 15/04/2022 |
| TS Date | 23 Mar 2022 |
|---|---|
| Estimate Approval | 23 Mar 2022 |
| NIT Approval | 23 Mar 2022 |
| Tender Closing | 28 Mar 2022 |
| Technichal Pre-Qualification | 30 Mar 2022 |
| Price bid opening | 30 Mar 2022 |
| Workorder Date | 31 Mar 2022 |
|---|---|
| NA | 01 Apr 2022 |
| Madathara PH Sn - AE |
| Date: 06/05/2022 |
Work has been completed | 100% Completed
100% work completed, Bill submitted to sub division.
| Madathara PH Sn - AE |
| Date: 02/05/2022 |
Work has been completed | 100% Completed
100% Completed.