Status Date |
Overall Project Status |
Project Officer |
Contact |
30 Mar 2024 |
PACKAGE 1 - Pipe supply completed. DI pipe - Total 22142 / laid -6030m. PVC pipe - Total 43680/ laid -38400m. 20 mm MDPE for service connection - 87570 m / Supplied 20000 m / laid - 15000 m. 9 LL OHSR Vadachira and 7LL OHSR Nirappath - work completed. PWD NH Road Cutting permission need to obtain for NH 766 (14.9)ROW application Row/1015759/19902,ROW/1015759/19904 PWD Road cutting permission need to obtain for Sulthan bathery - Noolpuzha road (0/0 to 0/50 Km). Morth Application No: 20220804/1/5/16748/1332, 20220919/1/5/16748/1481. Total bill submitted 18,47,53,832.00 (contractors bill - 15,34,62,553.00) -(PWD - 3,12,91,279.00). PACKAGE 2 - Pipe supply completed. DI pipe Total - 6690 m / Supplied 6682.5 m / laid 4175.8 m. PVC pipe Total - 52815 m / Supplied 52824 m / laid 48100m. PVC & MDPE for service connection 66780 m / supplied 35000 m / laid 14600 m. Kalluvayal distribution system partially charged. MDPE pipe laying work in progress. PWD NH road cutting permission need to obtain for 0/000-5/590 Km (NH766) ROW application ROW/1015759/19903. Morth Application No: 20220804/ 1/5/16748/ 1331, 20220919/1/5/16748/1484 . Total bill Submitted- 16,32,31,668.00 (Road reformation - 4,95,39,715.00 , Contractors bill - 11,36,91,953.00). PACKAGE 3 - Work completed, Final bill submitted. |
Kozhikode Project Dn EE |
|
13 Feb 2024 |
PACKAGE 1 - Pipe supply completed. DI pipe - Total 22142 / laid -6030m. PVC pipe - Total 43680/ laid -38400m. 20 mm MDPE for service connection - 87570 m / Supplied 20000 m / laid - 15000 m. 9 LL OHSR Vadachira and 7LL OHSR Nirappath - work completed. PWD NH Road Cutting permission need to obtain for NH 766 (14.9)ROW application Row/1015759/19902,ROW/1015759/19904 PWD Road cutting permission need to obtain for Sulthan bathery - Noolpuzha road (0/0 to 0/50 Km). Morth Application No: 20220804/1/5/16748/1332, 20220919/1/5/16748/1481. Total bill submitted 18,47,53,832.00 (contractors bill - 15,34,62,553.00) -(PWD - 3,12,91,279.00). PACKAGE 2 - Pipe supply completed. DI pipe Total - 6690 m / Supplied 6682.5 m / laid 4175.8 m. PVC pipe Total - 52815 m / Supplied 52824 m / laid 48100m. PVC & MDPE for service connection 66780 m / supplied 35000 m / laid 14600 m. Kalluvayal distribution system partially charged. MDPE pipe laying work in progress. PWD NH road cutting permission need to obtain for 0/000-5/590 Km (NH766) ROW application ROW/1015759/19903. Morth Application No: 20220804/ 1/5/16748/ 1331, 20220919/1/5/16748/1484 . Total bill Submitted- 16,32,31,668.00 (Road reformation - 4,95,39,715.00 , Contractors bill - 11,36,91,953.00). PACKAGE 3 -Pipe supply completed. DI pipe total - 2948 m / Supplied 2944.5 m / laid - 2944 m. PVC pipe total - 39573 m / Supplied 39630m / laid 37150 m. PVC & MDPE for service connection Total - 23396 / Laid 12800m. Kallupady OHSR retaining wall completed. Kaduvakuzhi retaining wall completed. Distribution from 7 LL OHSR Kallupady charged and Karyampady partially charged . 1050 HTCs completed. connection work in progress. PWD NH road cutting permission need to obtain for 3.5 Km ROW application ROW/1015759/19905. Morth Application No: 20220919/1/5/16748/1487. Total bill submitted - 5,97,73,708.00/- ( Road reformation - 42,91,176.00,contractors bill - 5,54,82,532.00). |
Kozhikode Project Dn AE5 |
|
09 Jan 2024 |
PACKAGE 1 - Pipe supply completed. DI pipe - Total 22142 / laid -6030m. PVC pipe - Total 43680/ laid -38400m. 20 mm MDPE for service connection - 87570 m / Supplied 20000 m / laid - 15000 m. 9 LL OHSR Vadachira and 7LL OHSR Nirappath - work completed. PWD NH Road Cutting permission need to obtain for NH 766 (14.9)ROW application Row/1015759/19902,ROW/1015759/19904 PWD Road cutting permission need to obtain for Sulthan bathery - Noolpuzha road (0/0 to 0/50 Km). Morth Application No: 20220804/1/5/16748/1332, 20220919/1/5/16748/1481. Total bill submitted 18,47,53,832.00 (contractors bill - 15,34,62,553.00) -(PWD - 3,12,91,279.00). PACKAGE 2 - Pipe supply completed. DI pipe Total - 6690 m / Supplied 6682.5 m / laid 4175.8 m. PVC pipe Total - 52815 m / Supplied 52824 m / laid 48100m. PVC & MDPE for service connection 66780 m / supplied 35000 m / laid 14600 m. Kalluvayal distribution system partially charged. MDPE pipe laying work in progress. PWD NH road cutting permission need to obtain for 0/000-5/590 Km (NH766) ROW application ROW/1015759/19903. Morth Application No: 20220804/ 1/5/16748/ 1331, 20220919/1/5/16748/1484 . Total bill Submitted- 16,32,31,668.00 (Road reformation - 4,95,39,715.00 , Contractors bill - 11,36,91,953.00). PACKAGE 3 -Pipe supply completed. DI pipe total - 2948 m / Supplied 2944.5 m / laid - 2944 m. PVC pipe total - 39573 m / Supplied 39630m / laid 37150 m. PVC & MDPE for service connection Total - 23396 / Laid 12800m. Kallupady OHSR retaining wall completed. Kaduvakuzhi retaining wall completed. Distribution from 7 LL OHSR Kallupady charged and Karyampady partially charged . 1050 HTCs completed. connection work in progress. PWD NH road cutting permission need to obtain for 3.5 Km ROW application ROW/1015759/19905. Morth Application No: 20220919/1/5/16748/1487. Total bill submitted - 5,97,73,708.00/- ( Road reformation - 42,91,176.00,contractors bill - 5,54,82,532.00). |
Kozhikode Project Dn AE5 |
|
12 Dec 2023 |
PACKAGE 1 - Pipe supply completed. DI pipe - Total 22142 / laid -6030m. PVC pipe - Total 43680/ laid -38400m. 20 mm MDPE for service connection - 87570 m / Supplied 20000 m / laid - 15000 m. 9 LL OHSR Vadachira and 7LL OHSR Nirappath - work completed. PWD NH Road Cutting permission need to obtain for NH 766 (14.9)ROW application Row/1015759/19902,ROW/1015759/19904 PWD Road cutting permission need to obtain for Sulthan bathery - Noolpuzha road (0/0 to 0/50 Km). Morth Application No: 20220804/1/5/16748/1332, 20220919/1/5/16748/1481. Total bill submitted 18,47,53,832.00 (contractors bill - 15,34,62,553.00) -(PWD - 3,12,91,279.00). PACKAGE 2 - Pipe supply completed. DI pipe Total - 6690 m / Supplied 6682.5 m / laid 4175.8 m. PVC pipe Total - 52815 m / Supplied 52824 m / laid 48100m. PVC & MDPE for service connection 66780 m / supplied 35000 m / laid 14600 m. Kalluvayal distribution system partially charged. MDPE pipe laying work in progress. PWD NH road cutting permission need to obtain for 0/000-5/590 Km (NH766) ROW application ROW/1015759/19903. Morth Application No: 20220804/ 1/5/16748/ 1331, 20220919/1/5/16748/1484 . Total bill Submitted- 16,32,31,668.00 (Road reformation - 4,95,39,715.00 , Contractors bill - 11,36,91,953.00). PACKAGE 3 -Pipe supply completed. DI pipe total - 2948 m / Supplied 2944.5 m / laid - 2944 m. PVC pipe total - 39573 m / Supplied 39630m / laid 37150 m. PVC & MDPE for service connection Total - 23396 / Laid 12800m. Kallupady OHSR retaining wall completed. Kaduvakuzhi retaining wall completed. Distribution from 7 LL OHSR Kallupady charged and Karyampady partially charged . 1050 HTCs completed. connection work in progress. PWD NH road cutting permission need to obtain for 3.5 Km ROW application ROW/1015759/19905. Morth Application No: 20220919/1/5/16748/1487. Total bill submitted - 5,97,73,708.00/- ( Road reformation - 42,91,176.00,contractors bill - 5,54,82,532.00). |
Kozhikode Project Dn AE5 |
|
15 Nov 2023 |
PACKAGE 1 - Pipe supply completed. DI pipe - Total 22142 / laid -6030m. PVC pipe - Total 43680/ laid -38400m. 20 mm MDPE for service connection - 87570 m / Supplied 20000 m / laid - 15000 m. 9 LL OHSR Vadachira and 7LL OHSR Nirappath - work completed. PWD NH Road Cutting permission need to obtain for NH 766 (14.9)ROW application Row/1015759/19902,ROW/1015759/19904 PWD Road cutting permission need to obtain for Sulthan bathery - Noolpuzha road (0/0 to 0/50 Km). Morth Application No: 20220804/1/5/16748/1332, 20220919/1/5/16748/1481. Total bill submitted 18,47,53,832.00 (contractors bill - 15,34,62,553.00) -(PWD - 3,12,91,279.00). PACKAGE 2 - Pipe supply completed. DI pipe Total - 6690 m / Supplied 6682.5 m / laid 4175.8 m. PVC pipe Total - 52815 m / Supplied 52824 m / laid 48100m. PVC & MDPE for service connection 66780 m / supplied 35000 m / laid 14600 m. Kalluvayal distribution system partially charged. MDPE pipe laying work in progress. PWD NH road cutting permission need to obtain for 0/000-5/590 Km (NH766) ROW application ROW/1015759/19903. Morth Application No: 20220804/ 1/5/16748/ 1331, 20220919/1/5/16748/1484 . Total bill Submitted- 16,32,31,668.00 (Road reformation - 4,95,39,715.00 , Contractors bill - 11,36,91,953.00). PACKAGE 3 -Pipe supply completed. DI pipe total - 2948 m / Supplied 2944.5 m / laid - 2944 m. PVC pipe total - 39573 m / Supplied 39630m / laid 37150 m. PVC & MDPE for service connection Total - 23396 / Laid 12800m. Kallupady OHSR retaining wall completed. Kaduvakuzhi retaining wall completed. Distribution from 7 LL OHSR Kallupady charged and Karyampady partially charged . 1050 HTCs completed. connection work in progress. PWD NH road cutting permission need to obtain for 3.5 Km ROW application ROW/1015759/19905. Morth Application No: 20220919/1/5/16748/1487. Total bill submitted - 5,97,73,708.00/- ( Road reformation - 42,91,176.00,contractors bill - 5,54,82,532.00). |
Kozhikode Project Dn AE5 |
|