RKI CWSS to Sulthan bathery Municipality, Noolpuzha and Muttil Panchayath in Wayanad District

Project RKI CWSS to Sulthan bathery Municipality, Noolpuzha and Muttil Panchayath in Wayanad District
Project Code WYDRKI03202423
Type Main project
Funding Agency RKI
Category RKI
Type of scheme Water Supply
Scheme 5475-00-115-94-05
Description 1. Construction of 9LL OHSR at Vadachira with booster station and7LL OHSR at NIrappath. 2. Laying Clear wtaer Gravity line from Kalluvayal to OHSR at Vadachira, Nirappath and St. Mary's college using 400mm DI pipe 3105m, 350mm DI pipe 2745m, 250mm Di pipe 1675m, 200mm DI pipe 5205m and 150mm DI pipe 47m 3. .Laying distribution lines from Vadchira- 28295m, Nirappath 24655m, Kalluvayal OHSR 35930m St.Mary's college 23515m, Kallupady 25949m and Kariyambadi 16572m 4.Retaining wall, compound wall and approach road at Kallupady, Kaduvakuzhi,karapuzha and Ambalawayal. 5 Providing 19850 FHTC. 6. O & M for 10 years after DLP of 18 months.
Status On-going
District Wayanad
Executing Office Kozhikode Project Dn
AS Amount (Rs) 640000000
AS Number GO (Rt) No. 123/2020/P&EA
TS Amount (Rs) 625000000
TS Number TS/2020-21/2020/7216,7382,8280
Total Bill Submitted (Rs) 407759208
Total Bill Paid (Rs) 407759208
Population Benefitted 90000
Capacity in MLD 16.00
Actual Project Completion Date 31 Oct 2023
Coverage Envisaged for 100 % coverage in Sulthan bathery Municipality Noolpuzha and Partial covarage in Muttil Panchayaths
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 RKI-CWSS to Sulthan bathery Municipality Noolpuzha and Muttil Panchayath in Wayanad District Phase -II package-II Kozhikode Project Dn
2 RKI CWSS TO Sulthan Bathery Municipality , Noolpuzha and Muttil Panchayath in Wayanad District Phase-II Package-III Kozhikode Project Dn
3 RKI-CWSS to Sulthan Bathery Noolpuzha and Muttil Panchayaths in Wayanad District Phase -II Package-1 Kozhikode Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
30 Mar 2024 PACKAGE 1 - Pipe supply completed. DI pipe - Total 22142 / laid -6030m. PVC pipe - Total 43680/ laid -38400m. 20 mm MDPE for service connection - 87570 m / Supplied 20000 m / laid - 15000 m. 9 LL OHSR Vadachira and 7LL OHSR Nirappath - work completed. PWD NH Road Cutting permission need to obtain for NH 766 (14.9)ROW application Row/1015759/19902,ROW/1015759/19904 PWD Road cutting permission need to obtain for Sulthan bathery - Noolpuzha road (0/0 to 0/50 Km). Morth Application No: 20220804/1/5/16748/1332, 20220919/1/5/16748/1481. Total bill submitted 18,47,53,832.00 (contractors bill - 15,34,62,553.00) -(PWD - 3,12,91,279.00). PACKAGE 2 - Pipe supply completed. DI pipe Total - 6690 m / Supplied 6682.5 m / laid 4175.8 m. PVC pipe Total - 52815 m / Supplied 52824 m / laid 48100m. PVC & MDPE for service connection 66780 m / supplied 35000 m / laid 14600 m. Kalluvayal distribution system partially charged. MDPE pipe laying work in progress. PWD NH road cutting permission need to obtain for 0/000-5/590 Km (NH766) ROW application ROW/1015759/19903. Morth Application No: 20220804/ 1/5/16748/ 1331, 20220919/1/5/16748/1484 . Total bill Submitted- 16,32,31,668.00 (Road reformation - 4,95,39,715.00 , Contractors bill - 11,36,91,953.00). PACKAGE 3 - Work completed, Final bill submitted. Kozhikode Project Dn EE
13 Feb 2024 PACKAGE 1 - Pipe supply completed. DI pipe - Total 22142 / laid -6030m. PVC pipe - Total 43680/ laid -38400m. 20 mm MDPE for service connection - 87570 m / Supplied 20000 m / laid - 15000 m. 9 LL OHSR Vadachira and 7LL OHSR Nirappath - work completed. PWD NH Road Cutting permission need to obtain for NH 766 (14.9)ROW application Row/1015759/19902,ROW/1015759/19904 PWD Road cutting permission need to obtain for Sulthan bathery - Noolpuzha road (0/0 to 0/50 Km). Morth Application No: 20220804/1/5/16748/1332, 20220919/1/5/16748/1481. Total bill submitted 18,47,53,832.00 (contractors bill - 15,34,62,553.00) -(PWD - 3,12,91,279.00). PACKAGE 2 - Pipe supply completed. DI pipe Total - 6690 m / Supplied 6682.5 m / laid 4175.8 m. PVC pipe Total - 52815 m / Supplied 52824 m / laid 48100m. PVC & MDPE for service connection 66780 m / supplied 35000 m / laid 14600 m. Kalluvayal distribution system partially charged. MDPE pipe laying work in progress. PWD NH road cutting permission need to obtain for 0/000-5/590 Km (NH766) ROW application ROW/1015759/19903. Morth Application No: 20220804/ 1/5/16748/ 1331, 20220919/1/5/16748/1484 . Total bill Submitted- 16,32,31,668.00 (Road reformation - 4,95,39,715.00 , Contractors bill - 11,36,91,953.00). PACKAGE 3 -Pipe supply completed. DI pipe total - 2948 m / Supplied 2944.5 m / laid - 2944 m. PVC pipe total - 39573 m / Supplied 39630m / laid 37150 m. PVC & MDPE for service connection Total - 23396 / Laid 12800m. Kallupady OHSR retaining wall completed. Kaduvakuzhi retaining wall completed. Distribution from 7 LL OHSR Kallupady charged and Karyampady partially charged . 1050 HTCs completed. connection work in progress. PWD NH road cutting permission need to obtain for 3.5 Km ROW application ROW/1015759/19905. Morth Application No: 20220919/1/5/16748/1487. Total bill submitted - 5,97,73,708.00/- ( Road reformation - 42,91,176.00,contractors bill - 5,54,82,532.00). Kozhikode Project Dn AE5
09 Jan 2024 PACKAGE 1 - Pipe supply completed. DI pipe - Total 22142 / laid -6030m. PVC pipe - Total 43680/ laid -38400m. 20 mm MDPE for service connection - 87570 m / Supplied 20000 m / laid - 15000 m. 9 LL OHSR Vadachira and 7LL OHSR Nirappath - work completed. PWD NH Road Cutting permission need to obtain for NH 766 (14.9)ROW application Row/1015759/19902,ROW/1015759/19904 PWD Road cutting permission need to obtain for Sulthan bathery - Noolpuzha road (0/0 to 0/50 Km). Morth Application No: 20220804/1/5/16748/1332, 20220919/1/5/16748/1481. Total bill submitted 18,47,53,832.00 (contractors bill - 15,34,62,553.00) -(PWD - 3,12,91,279.00). PACKAGE 2 - Pipe supply completed. DI pipe Total - 6690 m / Supplied 6682.5 m / laid 4175.8 m. PVC pipe Total - 52815 m / Supplied 52824 m / laid 48100m. PVC & MDPE for service connection 66780 m / supplied 35000 m / laid 14600 m. Kalluvayal distribution system partially charged. MDPE pipe laying work in progress. PWD NH road cutting permission need to obtain for 0/000-5/590 Km (NH766) ROW application ROW/1015759/19903. Morth Application No: 20220804/ 1/5/16748/ 1331, 20220919/1/5/16748/1484 . Total bill Submitted- 16,32,31,668.00 (Road reformation - 4,95,39,715.00 , Contractors bill - 11,36,91,953.00). PACKAGE 3 -Pipe supply completed. DI pipe total - 2948 m / Supplied 2944.5 m / laid - 2944 m. PVC pipe total - 39573 m / Supplied 39630m / laid 37150 m. PVC & MDPE for service connection Total - 23396 / Laid 12800m. Kallupady OHSR retaining wall completed. Kaduvakuzhi retaining wall completed. Distribution from 7 LL OHSR Kallupady charged and Karyampady partially charged . 1050 HTCs completed. connection work in progress. PWD NH road cutting permission need to obtain for 3.5 Km ROW application ROW/1015759/19905. Morth Application No: 20220919/1/5/16748/1487. Total bill submitted - 5,97,73,708.00/- ( Road reformation - 42,91,176.00,contractors bill - 5,54,82,532.00). Kozhikode Project Dn AE5
12 Dec 2023 PACKAGE 1 - Pipe supply completed. DI pipe - Total 22142 / laid -6030m. PVC pipe - Total 43680/ laid -38400m. 20 mm MDPE for service connection - 87570 m / Supplied 20000 m / laid - 15000 m. 9 LL OHSR Vadachira and 7LL OHSR Nirappath - work completed. PWD NH Road Cutting permission need to obtain for NH 766 (14.9)ROW application Row/1015759/19902,ROW/1015759/19904 PWD Road cutting permission need to obtain for Sulthan bathery - Noolpuzha road (0/0 to 0/50 Km). Morth Application No: 20220804/1/5/16748/1332, 20220919/1/5/16748/1481. Total bill submitted 18,47,53,832.00 (contractors bill - 15,34,62,553.00) -(PWD - 3,12,91,279.00). PACKAGE 2 - Pipe supply completed. DI pipe Total - 6690 m / Supplied 6682.5 m / laid 4175.8 m. PVC pipe Total - 52815 m / Supplied 52824 m / laid 48100m. PVC & MDPE for service connection 66780 m / supplied 35000 m / laid 14600 m. Kalluvayal distribution system partially charged. MDPE pipe laying work in progress. PWD NH road cutting permission need to obtain for 0/000-5/590 Km (NH766) ROW application ROW/1015759/19903. Morth Application No: 20220804/ 1/5/16748/ 1331, 20220919/1/5/16748/1484 . Total bill Submitted- 16,32,31,668.00 (Road reformation - 4,95,39,715.00 , Contractors bill - 11,36,91,953.00). PACKAGE 3 -Pipe supply completed. DI pipe total - 2948 m / Supplied 2944.5 m / laid - 2944 m. PVC pipe total - 39573 m / Supplied 39630m / laid 37150 m. PVC & MDPE for service connection Total - 23396 / Laid 12800m. Kallupady OHSR retaining wall completed. Kaduvakuzhi retaining wall completed. Distribution from 7 LL OHSR Kallupady charged and Karyampady partially charged . 1050 HTCs completed. connection work in progress. PWD NH road cutting permission need to obtain for 3.5 Km ROW application ROW/1015759/19905. Morth Application No: 20220919/1/5/16748/1487. Total bill submitted - 5,97,73,708.00/- ( Road reformation - 42,91,176.00,contractors bill - 5,54,82,532.00). Kozhikode Project Dn AE5
15 Nov 2023 PACKAGE 1 - Pipe supply completed. DI pipe - Total 22142 / laid -6030m. PVC pipe - Total 43680/ laid -38400m. 20 mm MDPE for service connection - 87570 m / Supplied 20000 m / laid - 15000 m. 9 LL OHSR Vadachira and 7LL OHSR Nirappath - work completed. PWD NH Road Cutting permission need to obtain for NH 766 (14.9)ROW application Row/1015759/19902,ROW/1015759/19904 PWD Road cutting permission need to obtain for Sulthan bathery - Noolpuzha road (0/0 to 0/50 Km). Morth Application No: 20220804/1/5/16748/1332, 20220919/1/5/16748/1481. Total bill submitted 18,47,53,832.00 (contractors bill - 15,34,62,553.00) -(PWD - 3,12,91,279.00). PACKAGE 2 - Pipe supply completed. DI pipe Total - 6690 m / Supplied 6682.5 m / laid 4175.8 m. PVC pipe Total - 52815 m / Supplied 52824 m / laid 48100m. PVC & MDPE for service connection 66780 m / supplied 35000 m / laid 14600 m. Kalluvayal distribution system partially charged. MDPE pipe laying work in progress. PWD NH road cutting permission need to obtain for 0/000-5/590 Km (NH766) ROW application ROW/1015759/19903. Morth Application No: 20220804/ 1/5/16748/ 1331, 20220919/1/5/16748/1484 . Total bill Submitted- 16,32,31,668.00 (Road reformation - 4,95,39,715.00 , Contractors bill - 11,36,91,953.00). PACKAGE 3 -Pipe supply completed. DI pipe total - 2948 m / Supplied 2944.5 m / laid - 2944 m. PVC pipe total - 39573 m / Supplied 39630m / laid 37150 m. PVC & MDPE for service connection Total - 23396 / Laid 12800m. Kallupady OHSR retaining wall completed. Kaduvakuzhi retaining wall completed. Distribution from 7 LL OHSR Kallupady charged and Karyampady partially charged . 1050 HTCs completed. connection work in progress. PWD NH road cutting permission need to obtain for 3.5 Km ROW application ROW/1015759/19905. Morth Application No: 20220919/1/5/16748/1487. Total bill submitted - 5,97,73,708.00/- ( Road reformation - 42,91,176.00,contractors bill - 5,54,82,532.00). Kozhikode Project Dn AE5

Project Review

See All Review messages
Review Date Review Message Review Attended By
18 Jun 2021 PWD cutting permission will be obtained after 15.7.21 from PWD BG Shall be paid by KWA MLA IC Balakrishnan sir, AEE KWA, AE KWA, PWD AEE, PWD AE,

Duration & Sanction dates

Date of start of Project 14/10/2020
Scheduled date of Completion of the Project 05 May 2022
Expected date of Completion 31/12/2024

Processing Dates

AS Date 03 Mar 2020
TS Date 02 Jul 2020