Jal Jeevan Mission (JJM)-Phase II-Thirumarady GramaPanchayath-Construction of 2.5LL capacity of Sump cum Pump house at Vettimood and with leading Gravity mains(Part-5)-General Civil Work
Project |
Jal Jeevan Mission (JJM)-Phase II-Thirumarady GramaPanchayath-Construction of 2.5LL capacity of Sump cum Pump house at Vettimood and with leading Gravity mains(Part-5)-General Civil Work |
Project Code |
EKMJJM022215010 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Jal Jeevan Mission (JJM)-Phase II-Thirumarady Grama Panchayath-Construction of 2.5LL capacity of Sump cum Pump house at Vettimood and with leading Gravity mains(Part-5)-General Civil Work |
Status |
On-going |
District |
Ernakulam |
Executing Office |
Muvattupuzha PH Dn |
AS Amount (Rs) |
455756000
|
AS Number |
G.O.(Rt)No.134/2022/WRD dated 23/02/2022 |
TS Amount (Rs) |
59720000 |
TS Number |
TS/7291/2023_5_1_1 dated 22/05/2023 Reg No.3811/2023-2024 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
500 |
Capacity in MLD |
2.50 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Thirumarady Grama Panchayath |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission (JJM)-Phase II-Thirumarady GramaPanchayath-Construction of 2.5LL capacity of Sump cum Pump house at Vettimood and with leading Gravity mains(Part-5)-General Civil Work |
Elenji Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
22 Jun 2024 |
Painting completed |
Elanji PH Sn - AE |
|
31 May 2024 |
Painting completed |
Elanji PH Sn - AE |
|
24 May 2024 |
Painting completed |
Elanji PH Sn - AE |
|
14 May 2024 |
Painting completed |
Elanji PH Sn - AE |
|
08 May 2024 |
Painting completed |
Elanji PH Sn - AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
23/07/2023 |
Scheduled date of Completion of the Project |
22 Jul 2024 |
Expected date of Completion |
22/07/2024 |
Processing Dates
AS Date |
23 Feb 2022 |
TS Date |
22 May 2023 |