Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Jal Jeevan Mission (JJM)-JJM PHASE - III-JJM - Kannur - Padiyur-Kalliad Grama Panchayath-WSS to Padiyur-Vayathur - Phase III- Balance work - Part.I - Supplying and laying distribution system and providing FHTCs-Pipeline Work

Project Jal Jeevan Mission (JJM)-JJM PHASE - III-JJM - Kannur - Padiyur-Kalliad Grama Panchayath-WSS to Padiyur-Vayathur - Phase III- Balance work - Part.I - Supplying and laying distribution system and providing FHTCs-Pipeline Work
Project Code KNRJJM092210431P2
Type Package
Main Project Jal Jeevan Mission - Kannur District - Padiyur-Kalliad Grama Panchayath-WSS to Padiyur-Vayathur Phase III . Construction of 2.50LL OHSR,Supplying and Laying of Pumping main and Distribution System and providing FHTCs
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission (JJM)-JJM PHASE - III-JJM - Kannur - Padiyur-Kalliad Grama Panchayath-WSS to Padiyur-Vayathur - Phase III- Balance work - Part.I - Supplying and laying distribution system and providing FHTCs-Pipeline Work
Status On-going
District Kannur
Executing Office Irikkur HW Sn
Agreement Number
Agreement Date
TS Amount (Rs) 69800000
TS Number WRD/KWA-CE(NR)/EST_TS/15003/2023_26_1_1
Technical specification

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 07/11/2023
Scheduled date of Completion as per agreement 07 May 2024
Expected date of Completion 06/05/2024

Processing Dates

TS Date 16 Aug 2023
Estimate Approval 16 Aug 2023

Approval Dates

Workorder Date 19 Sep 2023
NA 01 Nov 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Thaliparamba WS Dn EE
Date: 29/06/2024

Work in progress | 33% Completed

Pipe partially supplied.8667 m pipe laid.

Thaliparamba WS Dn EE
Date: 28/06/2024

Work in progress | 33% Completed

Pipe partially supplied.8667 m pipe laid.