Project | Jal Jeevan Mission (JJM)-JJM PHASE - III-JJM - Kannur - Padiyur-Kalliad Grama Panchayath-WSS to Padiyur-Vayathur - Phase III- Balance work - Part.I - Supplying and laying distribution system and providing FHTCs-Pipeline Work |
---|---|
Project Code | KNRJJM092210431P2 |
Type | Package |
Main Project | Jal Jeevan Mission - Kannur District - Padiyur-Kalliad Grama Panchayath-WSS to Padiyur-Vayathur Phase III . Construction of 2.50LL OHSR,Supplying and Laying of Pumping main and Distribution System and providing FHTCs |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Jal Jeevan Mission (JJM)-JJM PHASE - III-JJM - Kannur - Padiyur-Kalliad Grama Panchayath-WSS to Padiyur-Vayathur - Phase III- Balance work - Part.I - Supplying and laying distribution system and providing FHTCs-Pipeline Work |
Status | On-going |
District | Kannur |
Executing Office | Irikkur HW Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 69800000 |
TS Number | WRD/KWA-CE(NR)/EST_TS/15003/2023_26_1_1 |
Technical specification |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 07/11/2023 |
---|---|
Scheduled date of Completion as per agreement | 07 May 2024 |
Expected date of Completion | 06/05/2024 |
TS Date | 16 Aug 2023 |
---|---|
Estimate Approval | 16 Aug 2023 |
Workorder Date | 19 Sep 2023 |
---|---|
NA | 01 Nov 2023 |
Thaliparamba WS Dn EE |
Date: 29/06/2024 |
Work in progress | 33% Completed
Pipe partially supplied.8667 m pipe laid.
Thaliparamba WS Dn EE |
Date: 28/06/2024 |
Work in progress | 33% Completed
Pipe partially supplied.8667 m pipe laid.