Project | JJM 2020-21 Laying distribution lines& providing functional house hold tap connections in Ongallur grama panchayath. |
---|---|
Project Code | PKDJJM122011885P1 |
Type | Package |
Main Project | JJM 2020-21 Laying distribution lines& providing functional house hold tap connections in Ongallur grama panchayath. |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Providing FHTC'S and laying distribution system |
Status | On-going |
District | Palakkad |
Executing Office | Palakkad Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 311300000 |
TS Number | TS/2021-2022/2021/37948Dated: 13-01-2022 |
Technical specification | Providing FHTC's and laying distribution Ongallur panchayath. |
Contractor | C T THAMBI (Mob: 9495321861) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 11/04/2022 |
---|---|
Scheduled date of Completion as per agreement | 11 Jan 2023 |
Expected date of Completion | 31/12/2024 |
TS Date | 13 Jan 2022 |
---|---|
Estimate Approval | 10 May 2021 |
NIT Approval | 16 Dec 2021 |
Tender Closing | 02 Feb 2022 |
Technichal Pre-Qualification | 31 Mar 2022 |
Price bid opening | 04 Apr 2022 |
Workorder Date | 11 Apr 2022 |
---|---|
NA | 05 May 2022 |
Palakkad Project Dn AEE3 |
Date: 27/06/2024 |
Work in progress | 67% Completed
Work in progress 120.052/ 174.70 km laying completed. Remaining pipe laying work progressing.3183/8298 House connections completed & 3064 nos Geo tagged & 0 FHTC's.
Palakkad Project Dn AEE3 |
Date: 26/06/2024 |
Work in progress | 67% Completed
Work in progress 120.052/ 174.70 km laying completed. Remaining pipe laying work progressing.3183/8298 House connections completed & 3064 nos Geo tagged & 0 FHTC's.