Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

JJM 2020-21 Laying distribution lines& providing functional house hold tap connections in Ongallur grama panchayath.

Project JJM 2020-21 Laying distribution lines& providing functional house hold tap connections in Ongallur grama panchayath.
Project Code PKDJJM122011885P1
Type Package
Main Project JJM 2020-21 Laying distribution lines& providing functional house hold tap connections in Ongallur grama panchayath.
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Providing FHTC'S and laying distribution system
Status On-going
District Palakkad
Executing Office Palakkad Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 311300000
TS Number TS/2021-2022/2021/37948Dated: 13-01-2022
Technical specification Providing FHTC's and laying distribution Ongallur panchayath.
Contractor C T THAMBI (Mob: 9495321861)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 11/04/2022
Scheduled date of Completion as per agreement 11 Jan 2023
Expected date of Completion 31/12/2024

Processing Dates

TS Date 13 Jan 2022
Estimate Approval 10 May 2021
NIT Approval 16 Dec 2021
Tender Closing 02 Feb 2022
Technichal Pre-Qualification 31 Mar 2022
Price bid opening 04 Apr 2022

Approval Dates

Workorder Date 11 Apr 2022
NA 05 May 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Palakkad Project Dn AEE3
Date: 27/06/2024

Work in progress | 67% Completed

Work in progress 120.052/ 174.70 km laying completed. Remaining pipe laying work progressing.3183/8298 House connections completed & 3064 nos Geo tagged & 0 FHTC's.

Palakkad Project Dn AEE3
Date: 26/06/2024

Work in progress | 67% Completed

Work in progress 120.052/ 174.70 km laying completed. Remaining pipe laying work progressing.3183/8298 House connections completed & 3064 nos Geo tagged & 0 FHTC's.