Project | Jal Jeevan Mission - Mallappuzhassery Panchayath |
---|---|
Project Code | PTAJJM092110801 |
Type | Main project |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Providing FHTC's and laying pipelines |
Status | On-going |
District | Pathanamthitta |
Executing Office | Adoor Project Dn |
AS Amount (Rs) | 137700000 |
AS Number | G.O.(Rt)No.489/2021/WRD |
TS Amount (Rs) | 128870000 |
TS Number | TS/2021-2022/2021/5155 |
Total Bill Submitted (Rs) | 20288528 |
Total Bill Paid (Rs) | 20288528 |
Population Benefitted | 10804 |
Capacity in MLD | 4.50 |
Actual Project Completion Date | 03 Apr 2023 |
Coverage | all 13 wards of Mallappuzhassery Grama Panchayath |
Implementation Schedule | Download |
Work Plan | Download |
No. | Project Name | Location | View |
---|---|---|---|
1 | Jal Jeevan Mission - Mallappuzhassery Grama Panchayath - Investigation survey of distribution system | Adoor Project Dn | |
2 | JJM -2022-23-WSS to Elanthoor- Mallappuzhasserry - Alteration of existing FHTC s in Mallappuzhasserry Grama panchayat | Adoor Project Dn | |
3 | JJM - Mallappuzhassery Panchayath - Pipe line extensions to various places in Mallappuzhassery panchayath and providing FHTC's (III SLSSC) | Adoor Project Dn |
Date of start of Project | 14/03/2022 |
---|---|
Scheduled date of Completion of the Project | 03 Apr 2023 |
Expected date of Completion | 03/04/2023 |
AS Date | 18 Sep 2021 |
---|---|
TS Date | 27 Nov 2021 |
Project Officers | View |
---|