Jal Jeevan Mission - CWSS to Eramala and Adjoining Seven Panchayats
Project Code
CLTJJM092111005
Type
Main project
Funding Agency
JJM
Category
JJM
Type of scheme
Water Supply
Scheme
4215-01-102-92-02
Description
Jal Jeevan Mission - CWSS to Eramala and Adjoining Seven Panchayats - Construction of 12 m Dia. Intake Well,47 MLD WTP,Raw water pumping main,Pump sets, GL Sump at RWPH Koorangottukadavu, Clear Water Pumping main, 35 LL capacity GLSR at Kappumala Velom,Clear Water Transmission Main,Reservoirs,Distribution System and Providing FHTCs in ERAMALA, AZHIYUR, ONCHIYAM,CHORODE, VILLYAPALLY, EDACHERY,PURAMERI and VELOM grama panchayats
Construction of 15 LL OHSR at Edakkandy kunnu in Onchiyam GP and providing FHTC
Vadakara WSP Sn
2
Construction of 15 LL OHSR at Valiyamal Supplying Laying distribution net work and providing FHTC in Villyapally GP
Vadakara WSP Sn
3
Construction of 20 LL OHSR at Industrial estate area, Supplying Laying distribution net work and providing FHTC in Chorode GP
Vadakara WSP Sn
4
Construction of 20 LL OHSR at Modakunnu Supplying laying distribution net work and providing FHTC in Eramala GP
Vadakara WSP Sn
5
JAL JEEVAN(JJM)-CWSS TO Eramala and adjoining seven panchayats in kozhikode district-Construction of 8 Lakh Ltre capacity OHSR at Vilathapuram Laying distribution system and providing FHTCs in Purameri panchayath ARUR ZONE 1
Perambra PH Sn
6
JAL JEEVAN MISSION – CWSS to Eramala and Adjoining 7 Panchayats in kozhikode district – Rehabititation of existing 1.20 lakhs litres capacity OHSR at Nirayil and Laying Distribution system and provding FHTCs in Purameri Panchayat – zone :1 Purameri
Purameri PH Sn
7
Jal Jeevan Mission - CWSS to Eramala and Adjoining Seven Panchayats
Vadakara WSP Sn
8
Jal Jeevan Mission (JJM)-CWSS to Eramala and adjoining 7 panchayath in Kozhikode district Laying Distribution network and providing FHTCs from Existing OHSR at Karappakkunnu for Zone 1 in Azhiyur panchayath
Vadakara WSP Sn
9
JAL JEEVAN MISSION(JJM)-CWSS to Eramala and Adjoining seven panchayats in Kozhikode District - Purameri GP- Rehabilitation of existing 6 lakhs Litres OHSR at Vilathapuram, Laying Distribution System and Providing FHTCs-Arur:Zone 2
Purameri PH Sn
10
JAL JEEVAN Misssion(JJM)-CWSS TO Eramala and adjoining seven panchayats in kozhikode district-Construction and commissioning of 14lakh litre (8LL +6LL) capacity GLSR at Muliyankunnu,Laying distribution system and providing FHTCs in Edacheri Grama panchayath
Purameri PH Sn
11
JJM-CWSS to Eramala and adjoining seven grama panchayaths in Kozhikode District Supllying laying distribution line along Crash road and Karakunnummal road in Onchiyam GP
Vadakara WSP Sn
12
JJM-CWSS to Eramala and adjoining seven grama panchayaths in Kozhikode District-Supplying laying pumping main from Panikkotti to Payamkuttimala
Vadakara WSP Sn
13
JJM-CWSS to Eramala and adjoining seven grama panchayaths in Kozhikode DistrictSupply Laying distribution line from proposed 35 Lakh liter GLSR at existing WTP site Kappumala and providing FHTC in Velom grama panchayath
Vadakara WSP Sn
14
Supplying laying distribution net work in Karappakkunnu Zone III and providing FHTC in Azhiyur GP
Vadakara WSP Sn
Overall Project Status
Status Date
Overall Project Status
Project Officer
Contact
25 Oct 2023
VILLYAPALLY PIPE 26.7 km HTC 0 TANK NOT STARTED LAND NOT DOCUMENTED PAYAMKUTTIMALA P MAIN COMPLETED INTER CONNECTION TO BE DONE TANK RENOVATION TO BE DONE ROAD REFORMATION ONGOING ERAMALA LAND NOT OBTAINED PIPE SUPPLY ORDER ISSUED NOT OBTAINED ONCHIYAM TENDER PROCESSING CRASH ROAD PIPE LAYING COMPLETED
Vatakara PH Sn - AE
25 Oct 2023
VELOM PIPE 49.8 km HTC 320 AZHIYUR ZONE I PIPE 12.86 km FHTC 586 ZONE II PIPE 2.7 km HTC 205 ZONE IIIPIPE 4.4 HTC 220 ZONE IV KOTTAMALAKUNNU 15 km HTC 102 CHORODE PIPE 16 km TANK PCC COLUMN BASE RCC COLUMN FOOTING ONGOING
Vatakara PH Sn - AE
25 Oct 2023
VELOM PIPE LAYING 49.8 KM HTC 300 AZHIYUR KARAPPAKUNNU ZONE I PIPE 12.86 KM FHTC 586 ZONE II PIPE 2.69 KM HTC 205 ZONE III PIPE 4.4 KM HTC 220 ZONE IV PIPE KOTTAMALAKUNNU PIPE 15 KM HTC 102
Vatakara PH Sn - AE
21 Oct 2023
distribution net work for 7 grama panchayaths started transmission main work awaiting PWD road permission, OHSR work started at Chorode
Vatakara PH Sn - AE
12 Oct 2023
distribution net work for 8 gramapanchayaths on going, Transmission main works pending for want of PWD permission, major PWD roads not got permitted for trenching. OHSR started at Chorodu