| Project | PACKAGE III- SUPPLYING , LAYING , TESTING AND COMMISSIONING OF TRANSMISSION MAIN FROM WTP AT EDAKKANAM TO SERVICE RESERVOIRS IN 5 PANCHAYATHS |
|---|---|
| Project Code | KNRJJM022213306P3 |
| Type | Package |
| Main Project | JJM-KANNUR DISTRICT- WSS TO TRIPPANGOTTUR & ADJOINING PANCHAYATHS |
| Funding Agency | JJM |
| Category | JJM |
| Type of scheme | Water Supply |
| Scheme | 4215-01-102-92-01 |
| Description | Supplying, laying ,testing and commissioning of DI transmission main from proposed 32 mld WTP at Edakkanam to Service Reservoirs in 5 Panchayaths |
| Status | On-going |
| District | Kannur |
| Executing Office | Mattannur Project Dn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 11791 |
| TS Number | 9083/2023-2024 |
| Technical specification | Supplying, laying ,testing and commissioning of DI transmission main from proposed 32 mld WTP at Edakkanam to Service Reservoirs in 5 Panchayaths |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 16/10/2023 |
|---|---|
| Scheduled date of Completion as per agreement | 15 Jul 2024 |
| Expected date of Completion | 31/12/2025 |
| TS Date | 16 Jul 2023 |
|---|---|
| Estimate Approval | 16 Jul 2023 |
| NIT Approval | 15 Jul 2023 |
| Tender Closing | 19 Aug 2023 |
| Technichal Pre-Qualification | 15 Jul 2023 |
| Price bid opening | 21 Aug 2023 |
| Workorder Date | 16 Sep 2023 |
|---|---|
| NA | 06 Oct 2023 |
| Mattannur Project Sn 2 AE |
| Date: 22/04/2026 |
Work in progress | 70% Completed
Total transmission main 49.767 km, in that pipe supplied is 48.517 km. 38.5 km pipe laying completed.700mmDI laying work in progress at muliyathode-Kaivelikkal road,800mm DI laying work is in progress at Kooranmukku-Naduvanad road. Ambalapuzha steel bridge pier foundation pcc completed footing RCC completed.Pier column work in progress.Permission letter received from NHAI-Kozhikode on dated.12/08/25 for laying pipe lines (700mm Dia MS Casing pipe with 1No. 200mm dia DI pipe & 1No. 90mm PVC carrier pipe) across Chokli-Perngadi Road ( underpass of Thalassery- Mahe Bypass-NH-66 ) crossing at Ch.185+550,Kaviyoor LVUP by push through method.Road restoration work in progress . at valiyavelicham-cheeratta-cheruvanchery road (3.5km).1400 m BM work completed, Aythara-Goshala road 2600m (GSB+WMM) completed.400m tarring completed.LSGD road 2km tarring completed..
| Mattannur Project Sn 2 AE |
| Date: 08/04/2026 |
Work in progress | 69% Completed
Total transmission main 49.767 km, in that pipe supplied is 44.656 km. 37.5 km pipe laying completed.700mmDI laying work in progress at muliyathode-Kaivelikkal road,800mm DI laying work is in progress at Kooranmukku-Naduvanad road. Ambalapuzha steel bridge pier foundation pcc completed footing RCC completed.Permission letter received from NHAI-Kozhikode on dated.12/08/25 for laying pipe lines (700mm Dia MS Casing pipe with 1No. 200mm dia DI pipe & 1No. 90mm PVC carrier pipe) across Chokli-Perngadi Road ( underpass of Thalassery- Mahe Bypass-NH-66 ) crossing at Ch.185+550,Kaviyoor LVUP by push through method.Road restoration work in progress . at valiyavelicham-cheeratta-cheruvanchery road (3.5km).1400 m BM work completed, Aythara-Goshala road 2600m (GSB+WMM) completed.400m tarring completed.LSGD road 2km tarring completed.Ambalapuzha steel bridge pier footing earth excavation and dewatering in final stage.