Project | TWSS Rehabilitation of the existing PSC pipe Transmission main with MS Pipe from Peroorkada to Manvila including interconnection and allied works. |
---|---|
Project Code | TVMKIIFB0518602P1 |
Type | Package |
Main Project | KIIFB : TWSS Rehabilitation of the existing PSC pipe Transmission main with MS pipes of various sizes from Peroorkada to Manvila including interconnection and allied works. |
Funding Agency | KIIFB |
Category | KIIFB |
Type of scheme | Water Supply |
Scheme | KIIFB |
Description | Laying 1218mm MS pipe from Peroorkada - Church JN -200m 1118mm MS pipe from Church to PErprrkada GLSR - 256m 1118mm MS pipe from Peroorkada tank to Kudappanakkunnu -1740 m 914mm MS pipe from Kudappanakkunnu to VRK Jn - 4415 m 818mm MS pipe from VRK Jn to Pongumoodu - 996 m 711mm MS pipe from Pongumoodu to Manvila GLSR - 5599 m 600mm DI from VRK Jn to Kariyam Jn -2165 M |
Status | On-going |
District | Thiruvananthapuram |
Executing Office | Trivandrum Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 602770000 |
TS Number | TS/2018-2019/2018/8971 |
Technical specification | Laying 1218mm MS pipe from Peroorkada - Church JN -200m 1118mm MS pipe from Church to PErprrkada GLSR - 256m 1118mm MS pipe from Peroorkada tank to Kudappanakkunnu -1740 m 914mm MS pipe from Kudappanakkunnu to VRK Jn - 4415 m 818mm MS pipe from VRK Jn to Pongumoodu - 996 m 711mm MS pipe from Pongumoodu to Manvila GLSR - 5599 m 600mm DI from VRK Jn to Kariyam Jn -2165 M |
Contractor | M/s. Tomco Engineering (P) Ltd JV with M/s. Krita Engineering (Mob: 9447082222) |
Issue date | Solved On | Action Taken On | Category | Description | Comments | Issue Status |
---|---|---|---|---|---|---|
01 Sep 2021 | Pending | Pending | Natural Calamities Related | Yellow alert declared. Heavy rain across the state. | No comments available. | Pending |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 24/10/2020 |
---|---|
Scheduled date of Completion as per agreement | 30 Mar 2022 |
Expected date of Completion | 31/08/2022 |
TS Date | 07 Mar 2019 |
---|---|
Estimate Approval | 07 Mar 2019 |
NIT Approval | 10 Apr 2019 |
Tender Closing | 13 Jun 2019 |
Technichal Pre-Qualification | 24 Aug 2019 |
Price bid opening | 19 Sep 2019 |
Workorder Date | 14 Jan 2020 |
---|---|
NA | 05 Feb 2020 |
Thiruvananthapuram Project AE3 |
Date: 02/08/2023 |
Work has started | 0% Completed
Work foreclosure orders issued. Agreement to be done.
Thiruvananthapuram Project AE3 |
Date: 29/07/2023 |
Work has started | 0% Completed
Work foreclosure orders issued. Agreement to be done.