- Home
- JJM-IEC Activities wall painting, painti...
JJM-IEC Activities wall painting, painting letters and sketches for the advertisement of JalJeevan Mission over the GL Tank Wall Under KWA Kolachery Section office at Padkkunnu including JJM Logos, Quotes, Related to water conservation etc.Complete.
Project |
JJM-IEC Activities wall painting, painting letters and sketches for the advertisement of JalJeevan Mission over the GL Tank Wall Under KWA Kolachery Section office at Padkkunnu including JJM Logos, Quotes, Related to water conservation etc.Complete. |
Project Code |
KNRJJM082012726 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
JJM-IEC Activities wall painting, painting letters and sketches for the advertisement of JalJeevan Mission over the GL Tank Wall Under KWA Kolachery Section office at Padikkunnu including JJM Logos, Quotes, Related to water conservation etc.Complete. |
Status |
On-going |
District |
Kannur |
Executing Office |
Kannur WS Dn |
AS Amount (Rs) |
158100000
|
AS Number |
GO541/2020/WRD |
TS Amount (Rs) |
490000 |
TS Number |
8649/2022-2023 |
Total Bill Submitted (Rs) |
|
Total Bill Paid (Rs) |
|
Population Benefitted |
|
Capacity in MLD |
|
Actual Project Completion Date |
Date is not specified |
Coverage |
|
Packages
No. |
Project Name |
Location |
View |
1 |
JJM-IEC Activities wall painting, painting letters and sketches for the advertisement of JalJeevan Mission over the GL Tank Wall Under KWA Kolachery Section office at Padkkunnu including JJM Logos, Quotes, Related to water conservation etc.Complete. |
Kolachery PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
25 Jun 2024 |
Work in progress. |
Kolachery PH Sn AE |
|
19 Jun 2024 |
Work in progress. |
Kolachery PH Sn AE |
|
12 Jun 2024 |
Work in progress. |
Kolachery PH Sn AE |
|
05 Jun 2024 |
Work in progress. |
Kolachery PH Sn AE |
|
28 May 2024 |
Work in progress. |
Kolachery PH Sn AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
01/11/2022 |
Scheduled date of Completion of the Project |
18 Dec 2022 |
Expected date of Completion |
31/01/2023 |
Processing Dates
AS Date |
20 Aug 2020 |
TS Date |
28 Jun 2022 |