Project | Jal Jeevan Mission (JJM)-Nellaya-Mappattukara PWD restoration -Nellaya JJM phase 2 pipe line restoration work for laying 300mm DI pipe from Nellaya to Marayamagalam-Pipeline Work |
---|---|
Project Code | PKDJJM09219392P2 |
Type | Package |
Main Project | JJM 2020-21- Supplying, laying, testing, commissioning and mace of distribution system and mace of distribution system and providing FHTCs (3042nos) in Nellaya Grama Panchayath- Phase II |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Jal Jeevan Mission (JJM)-Nellaya-Mappattukara PWD restoration -Nellaya JJM phase 2 pipe line restoration work for laying 300mm DI pipe from Nellaya to Marayamagalam-Pipeline Work |
Status | On-going |
District | Palakkad |
Executing Office | Pattambi PH Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 6482600 |
TS Number | TS/10300/2023_26_1_1 |
Technical specification | Nellaya-Mappattukara PWD restoration -Nellaya JJM phase 2 pipe line restoration work for laying 300mm DI pipe from Nellaya to Marayamagalam-Pipeline Work |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 25/12/2023 |
---|---|
Scheduled date of Completion as per agreement | 24 Jan 2024 |
Expected date of Completion | 24/01/2024 |
TS Date | 28 Nov 2023 |
---|---|
Estimate Approval | 28 Nov 2023 |
NIT Approval | 29 Nov 2023 |
Tender Closing | 11 Dec 2023 |
Technichal Pre-Qualification | 16 Jan 2024 |
Price bid opening | 13 Dec 2023 |
Workorder Date | 25 Dec 2023 |
---|---|
NA | 03 Jan 2024 |
Pattambi PH Sn AE |
Date: 26/06/2024 |
Work has started | 0% Completed
Agreement executed, Not started because of Pipe line work not completed .
Pattambi PH Sn AE |
Date: 22/06/2024 |
Work has started | 0% Completed
Agreement executed .