Project | Jala Jeevan Mission - 2021-22 - WSS to Chazhur, Thanniam and Anthikkad Panchayths in Thrissur District - Phase II - Providing distribution network and FHTC to Anthikkad Panchayath |
---|---|
Project Code | TCRJJM022212367P1 |
Type | Package |
Main Project | Jala Jeevan Mission - 2021-22 - WSS to Chazhur, Thanniam and Anthikkad Panchayths in Thrissur District - Phase II - Providing distribution network and FHTC to Anthikkad Panchayath |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Jala Jeevan Mission - 2021-22 - WSS to Chazhur, Thanniam and Anthikkad Panchayths in Thrissur District - Phase II - Providing distribution network and FHTC to Anthikkad Panchayath |
Status | On-going |
District | Thrissur |
Executing Office | Nattika Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 245208000 |
TS Number | TS/2021-2022/2021/38066 |
Technical specification | Providing Distribution Network and FHTC to Anthikad Panchayath |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 17/10/2022 |
---|---|
Scheduled date of Completion as per agreement | 22 Jun 2022 |
Expected date of Completion | 22/06/2023 |
TS Date | 25 Mar 2022 |
---|---|
Estimate Approval | 25 Mar 2022 |
NIT Approval | 25 Mar 2022 |
Tender Closing | 25 Apr 2022 |
Technichal Pre-Qualification | 26 Apr 2022 |
Price bid opening | 27 Apr 2022 |
Workorder Date | 23 Jun 2022 |
---|---|
NA | 12 Jul 2022 |
Nattika Project Dn AE 6 |
Date: 28/06/2024 |
Work in progress | 79% Completed
HTC works in progress.
Nattika Project Dn AE 6 |
Date: 27/06/2024 |
Work in progress | 79% Completed
HTC works in progress.