Jal Jeevan Mission(JJM)-5th SLSSC - Water Supply Scheme to Mulamkunnthukavu Grama Panchayath in Thrissur District-Supply and laying common pumping main from Athekkad to M.G Kavu-package-II

Project Jal Jeevan Mission(JJM)-5th SLSSC - Water Supply Scheme to Mulamkunnthukavu Grama Panchayath in Thrissur District-Supply and laying common pumping main from Athekkad to M.G Kavu-package-II
Project Code TCRJJM022213936P2
Type Package
Main Project Jal Jeevan Mission (JJM)-5th SLSSC -Water Supply Scheme to Mulamkunnathukavu Grama Panchayath in Thrissur District
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission(JJM)-5th SLSSC - Water Supply Scheme to Mulamkunnthukavu Grama Panchayath in Thrissur District-Supply and laying common pumping main from Athekkad to M.G Kavu-package-II
Status On-going
District Thrissur
Executing Office Thrissur WW Sn 1
Agreement Number
Agreement Date
TS Amount (Rs) 33910000
TS Number WRD/KWA-CE(CR)/EST_TS/2104/2022_5_1_1
Technical specification Jal Jeevan Mission(JJM)-5th SLSSC - Water Supply Scheme to Mulamkunnthukavu Grama Panchayath in Thrissur District-Supply and laying common pumping main from Athekkad to M.G Kavu-package-II
Contractor M B Pradeep (Mob: 9388024636)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 20/12/2022
Scheduled date of Completion as per agreement 25 Feb 2023
Expected date of Completion 31/07/2024

Processing Dates

TS Date 08 Oct 2022
Estimate Approval 08 Oct 2022
NIT Approval 08 Oct 2022
Tender Closing 03 Nov 2022
Technichal Pre-Qualification 03 Nov 2022
Price bid opening 05 Nov 2022

Approval Dates

Workorder Date 20 Dec 2022
NA 04 Jan 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Thrissur WW Sn - AE 1
Date: 28/06/2024

Work in progress | 33% Completed

Agreement executed. parallel work of Omdhar delayed..

Thrissur PH Dn EE
Date: 26/06/2024

Work in progress | 33% Completed

Agreement executed. parallel work of Omdhar delayed..