AMRUT-Water Efficient Thrissur (WET) Upgrade-Providing water supply 24 x 7 to Chembukavu DMA

Project AMRUT-Water Efficient Thrissur (WET) Upgrade-Providing water supply 24 x 7 to Chembukavu DMA
Project Code TCRAMRUT012415745
Type Main project
Funding Agency AMRUT
Category AMRUT
Type of scheme Water Supply
Scheme AMRUT
Description AMRUT-Water Efficient Thrissur (WET) Upgrade-Providing water supply 24 x 7 to Chembukavu DMA
Status On-going
District Thrissur
Executing Office Thrissur PH Dn
AS Amount (Rs) 85800000
AS Number G.O.(Rt)No.156/2024/LSGD
TS Amount (Rs) 20000000
TS Number WRD/KWA-CE(CR)/EST_TS/1301/2024_5_1_1 Dated: 31-01-2024, WRD/KWA-CE(CR)/EST_TS/971/2024_26_1_1 Dated: 25-01-2024
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date Date is not specified
Coverage AMRUT-Water Efficient Thrissur (WET) Upgrade-Providing water supply 24 x 7 to Chembukavu DMA

Packages

No. Project Name Location View
1 AMRUT-Water Efficient Thrissur(WET) Upgrade-Providing Water Supply 24 x 7 to Chembukkavu DMA-Package 2-Pipe laying -General Civil Work Thrissur WW Sn 1
2 AMRUT-Water Efficient Thrissur(WET) Upgrade-Providing Water Supply 24 x 7 to Chembukkavu DMA-Package I-Pipe laying Part 1-Pipeline Work Thrissur WW Sn 1

Overall Project Status

Status Date Overall Project Status Project Officer Contact
19 Apr 2024 Work in progress. Thrissur PH Dn EE
12 Apr 2024 PKG 1-Work order issued on 28.02.2024. Agreement executed on 12.03.2024.PKG 2- Work order issued on 20.02.2024. Agreement executed on 04.03.2024 Thrissur PH Dn EE
04 Apr 2024 PKG 1-Work order issued on 28.02.2024. Agreement executed on 12.03.2024.PKG 2- Work order issued on 20.02.2024. Agreement executed on 04.03.2024 Thrissur PH Dn EE
19 Mar 2024 PKG 1-Work order issued on 28.02.2024. Agreement executed on 12.03.2024.PKG 2- Work order issued on 20.02.2024. Agreement executed on 04.03.2024 Thrissur PH Dn EE
18 Mar 2024 PKG 2- Work order issued on 20.02.2024. Agreement executed on 04.03.2024 Thrissur PH Dn EE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 20/02/2024
Scheduled date of Completion of the Project 19 Mar 2024
Expected date of Completion 31/05/2024

Processing Dates

AS Date 19 Jan 2024
TS Date 31 Jan 2024

Other details