- Home
- JJM-Phase 2 CWSS Thariode, Pozhuthana, K...
JJM-Phase 2 CWSS Thariode, Pozhuthana, Kottathara, Vegapalli Panchayaths in Wayanad District Phase II
Project |
JJM-Phase 2 CWSS Thariode, Pozhuthana, Kottathara, Vegapalli Panchayaths in Wayanad District Phase II |
Project Code |
CLTJJM092111007 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
JJM-Phase 2 CWSS Thariode, Pozhuthana, Kottathara, Vegapalli Panchayaths in Wayanad District Phase II |
Status |
On-going |
District |
Wayanad |
Executing Office |
Kozhikode Project Dn |
AS Amount (Rs) |
1250200000
|
AS Number |
G.O.(Rt) No.134/2022/WRD |
TS Amount (Rs) |
|
TS Number |
TS/2022-2023/2022/26053 |
Total Bill Submitted (Rs) |
217160501 |
Total Bill Paid (Rs) |
217160501 |
Population Benefitted |
70940 |
Capacity in MLD |
8.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
TOTAL FHTCs - 14188Nos. |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission - CWSS to Thariyode, Pozhuthana, Kottathara and Vengapalli Panchayaths in Wayanad District - Providing FHTC to Thariyode Grama Panchayath (WTP sump) by Laying new Distribution system - Zone 2 and 3 -Pipeline Work |
Kozhikode Project Dn |
|
2 |
Jal Jeevan Mission (JJM)-CWSS To Thariode, Kottathara, Vengapally and Pozhuthana Panchayath Phase 2-Construction and commissioning of 3 LL OHSR and 2 LL OHSR, Supply, Laying testing and commissioning Clear water gravity main in Vengapally Panchayath- Part II (after cancellation of the estimate WRD/KWA-CE(NR)/EST/5360/2022_5_1_1 in DDFS) - General Civil Work |
Kozhikode Project Dn |
|
3 |
Jal Jeevan Mission (JJM) - CWSS to Thariyode, Pozhuthana, Kottathara and Vengapally Panchayaths in Wayanad District - Laying distribution system and providing FHTC in Zone 1,2,3,4 and 5 of Pozhuthana Panchayath |
Kozhikode Project Dn |
|
4 |
Jal Jeevan Mission (JJM)-CWSS to Thariyode, Pozhuthana, Kottathara and Vengappally Panchayaths in Wayanad District-Laying distribution system and providing FHTC in Vengappally Panchayath- Package 1 for Zone 1 and 2 |
Kozhikode Project Dn |
|
5 |
Jal Jeevan Mission (JJM)-CWSS to Thariyode, Pozhuthana, Kottathara and Vengappally Panchayaths in Wayanad District-Laying distribution system and Providing FHTC to Kottathara Panchayath |
Kozhikode Project Dn |
|
6 |
JJM-Phase II-CWSS to Thariyode,Pozhuthana,Kottathara and Vengapally Panchayath in Wayanad District-Providing FHTC to Thariyode Grama Panchayath(WTP Sump) by laying new distribution system zone I (4th SWSM 2104 FHTC) |
Kozhikode Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
10 Nov 2023 |
1)Vengapally - Total DI pipe - 5426m / Supplied - 0m / Laid - 0m ; Total PE pipe - 102499m / Supplied - 102259m / Laid - 40827m ; Total pipe- 113280m / Total pipe supplied- 102259m / Total pipe laid- 40827m. FHTC - 3164 ; HTC - 841. 2)Kottathara - Total PE pipe - 148198m / PE Supplied - 76618 m / PE Laid - 13924 m . Total DI pipe - 11817m / DI Supplied - 709 m / DI Laid - 484 m . FHTC - 2662; HTC - 83. 3)Thariyod 2&3 - Total DI pipe - 2241 m / Supplied - 2241 / Laid - 869 m, Total PE pipe 42678 m / Supplied - 27570 m/ Laid - 24230 m. Total pipe- 44919 / Total pipe supplied- 29811 / Total pipe laid- 25099. Total FHTC - 1000. HTC given- 710 4)Thariyod 1 - Total DI pipe - 5647m / Supplied - 5000 / Laid - 2020 , Total PE pipe 76039 m / Supplied - 76042/ Laid - 52151 . Total pipe - 81686 / Supplied - 81041 / laid - 54189. FHTC Total - 2104, HTC given - 1618 |
Kozhikode Project Dn AE4 |
|
05 Nov 2023 |
1)Vengapally - Total DI pipe - 5426m / Supplied - 0m / Laid - 0m ; Total PE pipe - 102499m / Supplied - 102259m / Laid - 40827m ; Total pipe- 113280m / Total pipe supplied- 102259m / Total pipe laid- 40827m. FHTC - 3164 ; HTC - 841. 2)Kottathara - Total PE pipe - 148198m / PE Supplied - 76618 m / PE Laid - 12588m . Total DI pipe - 11817m / DI Supplied - 709 m / DI Laid - 484 m . FHTC - 2662; HTC - 18. 3)Thariyod 2&3 - Total DI pipe - 2241 m / Supplied - 2241 / Laid - 869 m, Total PE pipe 42678 m / Supplied - 27570 m/ Laid - 24230 m. Total pipe- 44919 / Total pipe supplied- 29811 / Total pipe laid- 25099. Total FHTC - 1000. HTC given- 710 4)Thariyod 1 - Total DI pipe - 5647m / Supplied - 5000 / Laid - 2020 , Total PE pipe 76039 m / Supplied - 76042/ Laid - 52151 . Total pipe - 81686 / Supplied - 81041 / laid - 54189. FHTC Total - 2104, HTC given - 1618 |
Kozhikode Project Dn AE4 |
|
03 Nov 2023 |
1)Vengapally - Total DI pipe - 5426m / Supplied - 0m / Laid - 0m ; Total PE pipe - 102499m / Supplied - 102259m / Laid - 40187m ; Total pipe- 113280m / Total pipe supplied- 102259m / Total pipe laid- 40187m. FHTC - 3164 ; HTC - 800. 2)Kottathara - Total PE pipe - 148198m / PE Supplied - 76618 m / PE Laid - 12588m . Total DI pipe - 11817m / DI Supplied - 709 m / DI Laid - 484 m . FHTC - 2662; HTC - 18. 3)Thariyod 2&3 - Total DI pipe - 2241 m / Supplied - 2241 / Laid - 869 m, Total PE pipe 42678 m / Supplied - 27570 m/ Laid - 24230 m. Total pipe- 44919 / Total pipe supplied- 29811 / Total pipe laid- 25099. Total FHTC - 1000. HTC given- 710 4)Thariyod 1 - Total DI pipe - 5647m / Supplied - 5000 / Laid - 2020 , Total PE pipe 76039 m / Supplied - 76042/ Laid - 52151 . Total pipe - 81686 / Supplied - 81041 / laid - 54189. FHTC Total - 2104, HTC given - 1618 |
Kozhikode Project Dn AE4 |
|
05 Nov 2023 |
1)Vengapally - Total DI pipe - 5426m / Supplied - 0m / Laid - 0m ; Total PE pipe - 102499m / Supplied - 102259m / Laid - 41827m ; Total pipe- 113280m / Total pipe supplied- 102259m / Total pipe laid- 41827m. FHTC - 3164 ; HTC - 873. 2)Kottathara - Total PE pipe - 148198m / PE Supplied - 76618 m / PE Laid - 12588m . Total DI pipe - 11817m / DI Supplied - 709 m / DI Laid - 484 m . FHTC - 2662; HTC - 18. 3)Thariyod 2&3 - Total DI pipe - 2241 m / Supplied - 2241 / Laid - 869 m, Total PE pipe 42678 m / Supplied - 27570 m/ Laid - 24230 m. Total pipe- 44919 / Total pipe supplied- 29811 / Total pipe laid- 25099. Total FHTC - 1000. HTC given- 710 4)Thariyod 1 - Total DI pipe - 5647m / Supplied - 5000 / Laid - 2020 , Total PE pipe 76039 m / Supplied - 76042/ Laid - 52151 . Total pipe - 81686 / Supplied - 81041 / laid - 54189. FHTC Total - 2104, HTC given - 1618 |
Kozhikode Project Dn AE4 |
|
03 Nov 2023 |
1)Vengapally - Total DI pipe - 5426m / Supplied - 0m / Laid - 0m ; Total PE pipe - 102499m / Supplied - 102259m / Laid - 40827m ; Total pipe- 113280m / Total pipe supplied- 102259m / Total pipe laid- 40827m. FHTC - 3164 ; HTC - 841. 2)Kottathara - Total PE pipe - 148198m / PE Supplied - 76618 m / PE Laid - 12588m . Total DI pipe - 11817m / DI Supplied - 709 m / DI Laid - 484 m . FHTC - 2662; HTC - 18. 3)Thariyod 2&3 - Total DI pipe - 2241 m / Supplied - 2241 / Laid - 869 m, Total PE pipe 42678 m / Supplied - 27570 m/ Laid - 24230 m. Total pipe- 44919 / Total pipe supplied- 29811 / Total pipe laid- 25099. Total FHTC - 1000. HTC given- 710 4)Thariyod 1 - Total DI pipe - 5647m / Supplied - 5000 / Laid - 2020 , Total PE pipe 76039 m / Supplied - 76042/ Laid - 52151 . Total pipe - 81686 / Supplied - 81041 / laid - 54189. FHTC Total - 2104, HTC given - 1618 |
Kozhikode Project Dn AE4 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
06/10/2022 |
Scheduled date of Completion of the Project |
21 Mar 2023 |
Expected date of Completion |
31/12/2023 |
Processing Dates
AS Date |
23 Feb 2022 |
TS Date |
08 Jul 2022 |