JJM-WSS to Marayoor and Kanthalloor Panchayaths in Idukki District.
Project |
JJM-WSS to Marayoor and Kanthalloor Panchayaths in Idukki District. |
Project Code |
IDKJJM022211086 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
JJM-WSS to Marayoor and Kanthalloor Panchayaths in Idukki District. |
Status |
On-going |
District |
Idukki |
Executing Office |
Kattappana Project Dn |
AS Amount (Rs) |
835260000
|
AS Number |
GO(Rt)No.134/2022/WRD |
TS Amount (Rs) |
805354100 |
TS Number |
WRD/KWA-CE(CR)/EST_TS/7347/2022_5_3_2 Dated: 24-04-2023 |
Total Bill Submitted (Rs) |
606245 |
Total Bill Paid (Rs) |
606245 |
Population Benefitted |
23362 |
Capacity in MLD |
6.50 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Marayoor and Kanthalloor Panchayath |
Packages
No. |
Project Name |
Location |
View |
1 |
Package 1- JJM-WSS to Well cum Pump house and Transformer control room atMarayoor and Kanthalloor(Pambar river zone) Panchayaths in Idukki District. |
Project Division Kattapana |
|
2 |
Package 4-JJM - WSS to Marayoor and Kanthallor Raw water pumping main (Pattissery dam zone) Panchayath in Idukki District |
Project Division Kattapana |
|
3 |
Package 5-JJM - WSS to Marayoor and Kanthallor(Pattissery dam zone) Panchayath in Idukki District |
Project Division Kattapana |
|
4 |
Package 6 - JJM-WSS to Marayoor and Kanthalloor -3 MLD Plant at Kanthalloor(Pattissery dam) |
Project Division Kattapana |
|
5 |
PACKAGE 7 - JJM CWSS to Marayoor and Kanthalloor Panchayths in Idukki District Construction of Sump cum pumphouse and Supply and erection of pump sets at Pampanpara |
Project Division Kattapana |
|
6 |
Package III - JJM-WSS to Marayoor -3.5 MLD Plant at Indira Nagar Community Hall/Njaval odakdi s t kudi |
Project Division Kattapana |
|
7 |
Package II-JJM - WSS to Marayoor and Kanthallor(Pambar river zone) Panchayath in Idukki District |
Project Division Kattapana |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
24 Jun 2024 |
Package I-Tender invited, Package II-Pipe laying, Package III-Tender invited Package 4-Tender invited Package 5 -Work in progress Package 6 -Tender invited 7-Tender invite |
Kattapana Project Dn AE4 |
|
24 Jun 2024 |
Package I-Tender invited, Package II-Pipe laying, Package III-Tender invited Package 4-Tender invited Package 5 -Work in progress Package 6 -Tender invited 7-Tender invite |
Kattapana Project Dn AE4 |
|
20 Jun 2024 |
Package I-Tender invited, Package II-Pipe laying, Package III-Tender invited Package 4-Tender invited Package 5 -Work in progress Package 6 -Tender invited 7-Tender invite |
Kattapana Project Dn AE4 |
|
17 Jun 2024 |
Package I-Tender invited, Package II-Pipe laying, Package III-Tender invited Package 4-Tender invited Package 5 -Work in progress Package 6 -Tender invited 7-Tender invite |
Kattapana Project Dn AE4 |
|
10 Jun 2024 |
Package I-Tender invited, Package II-Pipe laying, Package III-Tender invited Package 4-Tender invited Package 5 -Work in progress Package 6 -Tender invited7-Tender invite |
Kattapana Project Dn AE4 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
03/12/2023 |
Scheduled date of Completion of the Project |
04 Oct 2024 |
Expected date of Completion |
04/10/2024 |
Processing Dates
AS Date |
23 Feb 2022 |
TS Date |
24 Apr 2023 |