Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

JJM-2021-22 Providing FHTC in Kuzhimanna Grama Panchayath

Project JJM-2021-22 Providing FHTC in Kuzhimanna Grama Panchayath
Project Code MLPJJM12206133
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Providing Balance distribution system & 5548 FHTC in Kuzhimanna Grama panchayth
Status On-going
District Malappuram
Executing Office Malappuram Project Dn
AS Amount (Rs) 150000000
AS Number Go (rt) 777/2020/WRD
TS Amount (Rs) 148000000
TS Number TS/2022/13889
Total Bill Submitted (Rs) 100239967
Total Bill Paid (Rs) 100239967
Population Benefitted 35300
Capacity in MLD 1.00
Actual Project Completion Date 31 Dec 2022
Coverage kuzhimanna panchayath full coverage
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 FHTC in Kuzhimanna Grama Panchayth Project Division Malappuram
2 Phase II-Providing Balance distribution and Road restoration in Kuzhimanna Grama Panchayath Project Division Malappuram
3 Providing Balance Distribution including FHTC With PWD Road restoration in Kuzhimanna Grama Panchayath-Pipeline Work Project Division Malappuram

Overall Project Status

Status Date Overall Project Status Project Officer Contact
20 May 2024 2 work-tender processing Malapuram Proj Dn AE 4
14 Feb 2024 2 work- Tender under process Malapuram Proj Dn AE 4
11 Jul 2023 The work short closed as the lack of road cutting permission from PWD and shortage of GI pipe in rural concrete roads also the contractor not willing to execute the work in time extension. Estimate for the Balance works and FHTCs prepared and submitted. Malapuram Proj Dn AE 4
24 Jun 2023 Revised estimate submitted and inter connection work on going Malapuram Proj Dn AE 4
15 Jun 2023 Revised estimate submitted and inter connection work on going Malapuram Proj Dn AE 4

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 09/02/2022
Scheduled date of Completion of the Project 11 Sep 2022
Expected date of Completion 31/05/2023

Processing Dates

AS Date 24 Dec 2020
TS Date 02 Dec 2021

Other details

Project Officers View