Jal Jeevan Mission (JJM)- Jal Jeevan Mission (JJM)- ( Vandazhy HL) WSS to Vandazhi and Kizhakkenchery-DESIGN, CONSTRUCTION, COMMISSIONING,TRIAL RUNNING AND MAINTENANCE OF 14 LL OHSR AT KAVULUPARA, 12LL OHSR AT PALAKUZHY, SUPPLYING, LAYING, TESTING, COMMISSIONING AND MAINTANENCE OF CLEAR WATER PUMPING MAIN AND CLEAR WATER GRAVITY MAINS, SUPPLY AND ERECTION OF CLEAR WATER PUMPSETS, SUPPLYING, LAYING, TESTING AND COMMISSIONING OF DISTRIBUTION SYSTEM ALONG WITH PROVIDING FHTCs IN KIZHAKKANCHERY, VADAKKANCHERY AND KANNAMBRA PANCHAYATHS INCLUDING AND ROAD RESTORATION WORKS.-General Civil Work

Project Jal Jeevan Mission (JJM)- Jal Jeevan Mission (JJM)- ( Vandazhy HL) WSS to Vandazhi and Kizhakkenchery-DESIGN, CONSTRUCTION, COMMISSIONING,TRIAL RUNNING AND MAINTENANCE OF 14 LL OHSR AT KAVULUPARA, 12LL OHSR AT PALAKUZHY, SUPPLYING, LAYING, TESTING, COMMISSIONING AND MAINTANENCE OF CLEAR WATER PUMPING MAIN AND CLEAR WATER GRAVITY MAINS, SUPPLY AND ERECTION OF CLEAR WATER PUMPSETS, SUPPLYING, LAYING, TESTING AND COMMISSIONING OF DISTRIBUTION SYSTEM ALONG WITH PROVIDING FHTCs IN KIZHAKKANCHERY, VADAKKANCHERY AND KANNAMBRA PANCHAYATHS INCLUDING AND ROAD RESTORATION WORKS.-General Civil Work
Project Code PKDJJM022215618
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description DESIGN, CONSTRUCTION, COMMISSIONING,TRIAL RUNNING AND MAINTENANCE OF 14 LL OHSR AT KAVULUPARA, 12LL OHSR AT PALAKUZHY, SUPPLYING, LAYING, TESTING, COMMISSIONING AND MAINTANENCE OF CLEAR WATER PUMPING MAIN AND CLEAR WATER GRAVITY MAINS, SUPPLY AND ERECTION OF CLEAR WATER PUMPSETS, SUPPLYING, LAYING, TESTING AND Jal Jeevan Mission (JJM)- Jal Jeevan Mission (JJM)-WSS to Vandazhi and Kizhakkenchery-DESIGN, CONSTRUCTION, COMMISSIONING,TRIAL RUNNING AND MAINTENANCE OF 14 LL OHSR AT KAVULUPARA, 12LL OHSR AT PALAKUZHY, SUPPLYING, LAYING, TESTING, COMMISSIONING AND MAINTANENCE OF CLEAR WATER PUMPING MAIN AND CLEAR WATER GRAVITY MAINS, SUPPLY AND ERECTION OF CLEAR WATER PUMPSETS, SUPPLYING, LAYING, TESTING AND COMMISSIONING OF DISTRIBUTION SYSTEM ALONG WITH PROVIDING FHTCs IN KIZHAKKANCHERY, VADAKKANCHERY AND KANNAMBRA PANCHAYATHS INCLUDING AND ROAD RESTORATION WORKS.-General Civil Work
Status On-going
District Palakkad
Executing Office Chittur Project Dn
AS Amount (Rs) 1146700000
AS Number GO(Rt no 134/2022/WRD/TVM dtd 23.02.2022
TS Amount (Rs) 1095000000
TS Number WRD/KWA-CE(NR)/EST-TS /4882/2023 DTD 25.03.2023
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted 60586
Capacity in MLD 24.50
Actual Project Completion Date Date is not specified
Coverage VANDAZHY, VADAKKENCHERY , KIZHAKKENCHERY AND KANNAMBRA

Packages

No. Project Name Location View
1 Jal Jeevan Mission (JJM)- Jal Jeevan Mission (JJM)- ( Vandazhy HL) WSS to Vandazhi and Kizhakkenchery-DESIGN, CONSTRUCTION, COMMISSIONING,TRIAL RUNNING AND MAINTENANCE OF 14 LL OHSR AT KAVULUPARA, 12LL OHSR AT PALAKUZHY, SUPPLYING, LAYING, TESTING, COMMISSIONING AND MAINTANENCE OF CLEAR WATER PUMPING MAIN AND CLEAR WATER GRAVITY MAINS, SUPPLY AND ERECTION OF CLEAR WATER PUMPSETS, SUPPLYING, LAYING, TESTING AND COMMISSIONING OF DISTRIBUTION SYSTEM ALONG WITH PROVIDING FHTCs IN KIZHAKKANCHERY, VADAKKANCHERY AND KANNAMBRA PANCHAYATHS INCLUDING AND ROAD RESTORATION WORKS.-General Civil Work Project Division Chittur

Overall Project Status

Status Date Overall Project Status Project Officer Contact
16 May 2024 Work in progress | 7% Completed | 16/05/2024 pipe line laid for a length of 20.713km, out of 279km 1) 90 MM PVC 12.50 kg – 8540.2m 2) 90mm pvc 10 kg - 9931m 3) 80mm GI =2243m Chittur Project Dn - AE 3
09 May 2024 Work in progress | 7% Completed | 09/05/2024 pipe line laid for a length of 19.989km, out of 279km 1) 90 MM PVC 12.50 kg – 8540.2m 2) 90mm pvc 10 kg - 9931m 3) 80mm GI =1518m Chittur Project Dn - AE 3
02 May 2024 Work in progress | 7% Completed | 02/05/2024 pipe line laid for a length of 19.989km, out of 279km 1) 90 MM PVC 12.50 kg – 8540.2m 2) 90mm pvc 10 kg - 9931m 3) 80mm GI =1518m Chittur Project Dn - AE 3
25 Apr 2024 Work in progress | 7% Completed | 25/04/2024 pipe line laid for a length of 19.989km, out of 279km 1) 90 MM PVC 12.50 kg – 8540.2m 2) 90mm pvc 10 kg - 9931m 3) 80mm GI =1518m Chittur Project Dn - AE 3
19 Apr 2024 Work in progress | 7% Completed | 19/04/2024 pipe line laid for a length of 19.175km, out of 279km 1) 90 MM PVC 12.50 kg – 8540.2m 2) 90mm pvc 10 kg - 9332m 3) 80mm GI =1303m Chittur Project Dn - AE 3

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 03/07/2023
Scheduled date of Completion of the Project 02 Aug 2024
Expected date of Completion 31/12/2024

Processing Dates

AS Date 23 Feb 2022
TS Date 25 Mar 2023

Other details